Tillotson Construction had a wet time of it when building at David City in 1951

By Ronald Ahrens

“Wet pit,” notes the Tillotson Construction Co. record in its details of the David City job of 1951.

An icon for Nebraska 2020 road tripA Tillotson crew put up a single-leg, 180,000-bushel, reinforced-concrete elevator in the seat of Butler County during one of the wettest periods ever recorded in the prairie region.

“Most of Kansas and Missouri as well as large portions of Nebraska and Oklahoma had monthly precipitation totaling 200 percent of normal in May, 300 percent in June, and 400 percent in July of 1951,” says a report by the National Weather Service.

But the work went on. The new David City elevator was built on an original plan with five tanks, or silos, of 18 feet in diameter and rising 120 feet. There was a 13 by 17-foot center driveway, eight bins over the drive, and a total of 15 bins and overflow. “Dust Bin @ Ext.” observes a further note.

The elevator required 1,716 cubic yards of reinforced concrete, 20 yards of plain concrete for hoppers, and 81.16 tons of rebar.

The 21-inch-thick main slab extended over 60 by 55 feet, covering an area (“Act. Outside on Ground”) of 3,057 square feet. It sat over a 17-foot-deep pit. The design incorporated a full basement.

The slab supported 3,513 tons of reinforced concrete and 40 tons of plain concrete. With grain weighing 60 pounds per bushel, there was capacity for 5,400 tons of grain. Along with structural steel and machinery as well as hoppers, the the elevator was rated at 9,458 tons total loaded weight.

An elegant rounded cupola, or headhouse, sat atop the tanks. Its dimension were 19 feet wide, 38 feet long, and 27 1/3 feet high. With the moderately tall cupola and moderately deep pit, the centers of the leg’s head and boot pulleys were 154.83 feet apart.

The pulleys were 72 x 14 x 2 3/16 inches (boot) and 72 x 14 x 3 5/16 (head) and turned the at 42 revolutions per minute.

Calumet supplied the 330-inch, six-ply belt that was 14 inches wide. Cups of 12 x 6 inches were spaced at nine-inch intervals.

A 30-horsepower Howell motor delivered a theoretical leg capacity of 7,140 bushels per hours. Operating at 80 percent, it needed 27.6 hp to deliver actual capacity of 5,700 bushels per hour.

A 1.5-hp motor ran the manlift. The truck lift operated with a 7.5-hp Ehrsam motor.

A further note indicates, “300 Bu. Dryer Split Bin #7 for Dryer.”

2 comments on “Tillotson Construction had a wet time of it when building at David City in 1951

  1. Chandler Thomas says:

    Good Morning. In a previous post about David City, NE elevators, you questioned the contractor for the elevator with the square, stepped head house.I recall being in David City on a number of occasions in the late ’70’s or early ’80’s when that coop was considering building additional storage. The eventually built a new grain elevator on a rail siding outside of town. However, I measured up both elevators when they were considering annex storage. If memory serves correctly, the elevator with the square, stepped head house was an early project of Mid States Construction out of Omaha. Mid States was owned and managed by Gordon Erickson.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s