Goltry hails the new grain elevator in July 6, 1939 issue of the Leader newspaper

Grain Building Is the Work Of Omaha Firm

One of the largest wheat crops ever yielded by this section of the northwestern Oklahoma wheat belt was dumped into Goltry’s new 60,000 bushel elevator built for the Farmers’ Exchange of Goltry by the Tillotson construction company of Omaha, Nebraska,

The construction company operated by R.O and J.H. Tillotson, brothers, designers of modern concrete buildings, both of whom were in Goltry at various times during the progress of the building, was awarded the contract March 15. Shortly afterwards a crew of local workers began digging the pit, the first step in the actual construction of the new building.

Wheat was being dumped into the elevator at a time when the harvesting of wheat in this section was only beginning while electricians and skilled workers for the construction company were giving the building its finishing touches.

After the pit had been dug, a crew of 45 men–part of them local persons–was put to work by the company. Carpenters were building slip forms into which concrete was poured. The forms were four feet in height. As concrete was poured, the forms were moved upwards.

The forms were raised with jacks of which there were 48. All 48 jacks were turned by four men. Two turns of the jack screw raised the forms an inch and the jacks were turned in almost continuous operation.

The level of the forms was checked every hour in an effort to insure absolute accuracy. The Tillotson construction company used a new style of checking device in their job here. The company already had used five different kinds of checking devices during its various construction jobs. Employees of the company reported that the new device was the most accurate they had yet used.

The forms were raised an average of six feet every 10 hours. In the new checking device, targets were used in measuring distances with plumbs to keep the forms absolutely level all the way around at all times during their progress upwards.

The new style of checking system was not designed and made available until a short time previous to the date upon which the company began the Goltry job.

Before superintendent W.B. Morris, whose home is in Kansas City, left the job, 150,000 bushels of wheat had been put through the elevator. More than 85 carloads had been loaded from the elevator before Morris left. Each carload amounts to an average of 1,800 bushels. The machinery and equipment in the elevator were operating perfectly before the last of the company’s workers and the superintendent left the job.

“Everything ran smoothly with never a touch of trouble,” Morris, superintendent of the Goltry job for the Tillotson construction company, said.

A large amount of the responsibility for seeing that the day by day progress of the building was not interrupted at any time was delegated to Morris. However, Morris gave a great deal of the credit to the entire group of workers which included a number of local men. Morris said his company had “the best cooperation among the men working for us. We appreciate the interest shown by the people of the community and the efforts the men put forth endeavoring to keep the job going at the proper speed at all times,” Morris said.

The new elevator is 120 feet from the bottom of the basement to the top. The basement is four feet below the ground level and seven and a half feet below the floor. The capacity is 60,000 bushels.

A truck lift on the first floor of the elevator picks up trucks with ease in the process of dumping grain from the trucks into the pits. The new style of truck lift will not catch the radiator or damage the truck in any way.

Two pits into which grain is dumped hold 1,200 bushels. The first pit holds 850, the second 450.

Legs motivate the belt and cups and such a speed that the grain is elevated upwards into the bins at a rate of 60 bushels per minute.

At the top of the building, an automatic scale dumps 60 bushels per minute. The scale hold 10 bushels and automatically drops six times per minute.

A blowing system cleans wheat and sends the dust and chaff and foreign particles down a chute and into a compartment just above the first floor. At intervals this compartment is dumped into a truck and hauled away.

A fast cage type man lift–one of the fastest man lifts to be found in an elevator of the size of the new Goltry building–hoists the workers upward to the top of the building at a time saving rate of speed.

Among the various types of men working on the job–of which there were as many as 45 at the time the crew was running slip forms–were electricians, concrete workers, steel men, jack men, hoisting engineer, concrete mixer operator, finishers who smoothed the walls and the floors, painters, buggy men and wheel barrow men.

Front page caption:

Goltry’s new modern elevator building (above), built for the Farmers’ Exchange of Goltry by the Tillotson construction company of Omaha, Nebraska, is 120 feet in height, rising 116 feet above the ground level and falling four feet below the level of the ground. The capacity of the new building is 60,000 bushels and its modern machinery and equipment, all brand new, enable the operators of the Farmers’ Exchange to dump grain into the pit, elevate it, clean it with a modern blowing system, weigh it and load it into waiting box cars as rapidly as modern high speed trucks can bring it in. Photo exclusively for The Goltry Leader by Cochrane commercial photographers.

Inside page caption:

Approaching Goltry from the west a person would be afforded this view of the new Farmers’ Exchange elevator building (above) towering 116 feet toward the sky, its smooth, white walls reflecting with added brilliance the dazzling rays of the midsummer, afternoon sun. (Photo exclusively for The Goltry Leader by Cochrane commercial photographers).

In 1939 letter, Joe Tillotson asks about wheat allotment, reports on new concrete elevator

July 22, 1939

Dict. July 21

Mr. Warren Tillotson

Shields, Kansas

Dear Uncle Warren:

We have thought several times about writing to you to ask if there would be any possibility that we could get an allotment for not raising wheat on that land of Dad’s down there in Kansas.

Now of course it doesn’t seem right to us that the government should pay for this land being idle when there is really no intention of farming it, but we keep hearing of similar cases like this and even understand that where the local agent knows the owner of the land they are solicited and offered an allotment for this unused land.

We feel that you are probably familiar with this subject and if you have a few moments to spare, might drop us a line and let us know what you think about it.

We thought we would get out to see you and John sometime this summer but haven’t had a call anywhere near you so far. Most of our work this year has been down in Oklahoma, Kansas in the eastern part, Missouri in the western part, and eastern Iowa. We are enclosing a local newspaper from Goltry, Oklahoma which shows a job that we just finished. This is our first attempt at concrete construction and out of five similar jobs built in this same neighborhood our concrete by test shows to be the strongest, the machinery the best and fastest, and the insurance rate on this job is lower than any of the others; and as long as we didn’t lose any money on our first attempt at this line of work we feel that we would like to have more of this reinforced concrete construction work.

Don’t believe we answered John’s letter of April 5, as it came in right when we were the very busiest, but we still have hopes of getting out there to see both of you before the year is over.

We hope your wheat crop was good and that you may be coming up this way sometime soon and will stop and see us.

Respectfully,

Your nephew,

Joe

Rain delays and balky formwork hindered Grain Storage Construction Co. at Ceresco, Neb.

Lincoln Journal Star, Friday, Sep. 18, 1959

Grain Storage Construction Co. benefited from the expertise of Ted Morris, who had been employed by Tillotson Construction Co. As Tillotson’s activities declined in the late-1950s, the GSCC, of Council Bluffs, Iowa, stepped in to undertake construction of new grain elevators.

Here is news from the Fremont (Neb.) Tribune on July 24, 1959 as the company’s crew built an elevator of reinforced concrete next to a traditional wooden elevator at Ceresco, a village just 20 miles north of the Nebraska Capitol building in downtown Lincoln.

Weather, Difficulties Delay Bin Construction at Ceresco

CERESCO–The Farmers Cooperative Association’s new, 250,000-bushel capacity grain elevator being constructed here by Grain Storage Const. Co. of Council Bluffs, Iowa, is expected to be completed by Sept. 1, according to project foreman Doyle Elliott.

The elevator will have 120-foot high storage tanks, topped by a 42 1/2-foot scale house. Tank construction is one third complete.

* * *

Construction of the new elevator started April 1, but work progress was hampered by a lengthy rain spell during the initial weeks. Difficulty with the hydraulic hoists, which raise the movable wood form after concrete has been poured, caused a brief shutdown of pouring operations.

The wood frame held too tightly in some places and left a few unfilled pockets in the concrete shell of the storage tank walls. Construction workers are patching up the pockets and new concrete pouring should begin sometime next week.

Once the pouring begins the tank walls can be built up at the rate of 16 feet every 24 hours. “Most people judge progress in elevator construction by the outside appearance,” said Elliott. “They do not realize how much inside work has to be accomplished before you can proceed safely with the exterior work,” he added.

“We hope the elevator will be ready by Sept. 1,” said Farmers Co-op Assn. manager Leonard Palm. “We would like to get this year’s corn crop in. I think we will make it as there have been no serious construction flaws or delays so far,” he added. 

Editor’s note: Based on the Sep. 18, 1959 date of the Lincoln Journal Star’s photo and caption (top), GSCC did not manage to complete the elevator by the date the Co-op had hoped for.

We thank our friend Susan Allen for unearthing the clippings.

Tillotson Construction Co. alumnus Ted Morris leads new elevator job at Beatrice, Neb. in 1958

Beatrice (Neb.) Daily Sun, Oct. 28, 1958

The contract to build the 100,000 bushel elevator on the old Wiebe Lumber Co. property has already been let, August Grell said last night. He stated that the contractor is Ted Morris, Grain Storage Construction Co., Council Bluffs, Ia. They have materials on order and are ready to go to work, he stated. The Beatrice Concrete Co. has a sub-contract for furnishing the concrete for the structure, which is to be built at an estimated cost of $250,000.

Editor’s note: There is a discrepancy in capacity of the elevator as recorded in the two articles. We believe the 340,000-bushel figure is more likely correct.

The Lincoln Star, Dec. 27, 1958

Beatrice, Neb. — Construction has begun here on a new 340,000 bushel capacity grain elevator by the Farmer’s Co-Op. Being built by the Grain Storage Construction Co. of Council Bluffs, Ia., the elevator will consist of 8 concrete bins, 120 feet high with a 40-foot high headhouse on top to house lifting machinery.

We thank our friend Susan Allen for unearthing this and other clippings.

 

Beatrice Daily Sun, Dec. 26, 1958

Employees were on the move in 1959 for work on one of Tillotson’s last elevators

The Helena (Oklahoma) Star, Thursday, Jan. 22, 1959

Mr. and Mrs. Francis Dawson have moved into the former Thompson house, recently vacated by the Carl Jantz family, and Mr. and Mrs. Austin Brown live in a trailer house on the back of the lot, there.

The men are employed by the Tillotson Construction Co., that is building the new elevator at McWillie.

They came here from Texas.

We thank our friend Susan Allen for unearthing this and other clippings.

What were a timekeeper’s duties on a grain elevator construction project?

By Charles J. Tillotson

Editor’s note: The previous post about Charles Hauber, an employee of Tillotson Construction Co. in the mid-1950s, raises a question: What were a timekeeper’s duties on a grain elevator construction project?

The timekeeper’s duties were often directly proportionate to the project size. On small projects the timekeeper’s duties were performed by the job superintendent. If the size of the job warranted a full-time person, his duties would require him to daily monitor the laborers on the job and their hourly rate of pay, either by requiring each individual laborer to personally check in with him in the morning, thereby “starting the clock” for the labor to be performed for that day.

On larger projects with a given steady number of workmen on the job with constant types of duties being performed each day where personal check-in would take up too much time, the timekeeper would merely check out each laborer’s hours, task, and hourly rate for each workman via personal observation and contact throughout the day.

The timekeeper was also responsible for recording the hours worked by the on-site administration and supervision personnel, but usually the pay rate for these people, including himself, would be held confidential.

In any regard, no matter the job size, the responsibility of the timekeeper was to accrue, on a daily basis the name of each laborer, his hours worked, his job and his rate of pay. This daily tabulation for all labor and supervision personnel would then be transmitted to the accounting department in the Tillotson Construction Co.’s home office in Omaha.

The Accounting Department would then convert this information into the individual payroll checks to be issued to each workman. This was usually on a weekly basis. In many cases, where the job was in a remote area and there wasn’t enough time to transmit the payroll physically, the payroll checks were written on the job site by the timekeeper after receiving the amount of each check via the telephone from the Accounting Department.

The timekeeper’s job was a very important position requiring a person of integrity, honesty, and dependability–for without those key characteristics the possibility of achieving a successful and profitable project couldn’t be accomplished.

The Des Moines Tribune profiled Tillotson Construction Co. timekeeper Charles Hauber in 1955

By Herb Owens

DALLAS CENTER, IA–Charles Hauber, 21, timekeeper on a grain elevator construction project here, is living proof that “a weak chin” is not visual evidence of a lack of determination.

Seven years ago Hauber’s lower jaw suffered a major injury in an auto accident. A nerve was severed and, as a result, the natural growth and development of his chin was retarded.

Two years ago, Hauger spent a month at University Hospitals in Iowa City, where physicians and surgeons estimated his possibilities fro reconstruction of his lower jaw and chin.

By using bone from his hip, surgeons are hopeful that they can build a normal mandible for Hauber. Through use of cartilage, the youth’s chin would be rebuilt to normal appearance.

Long self-conscious about his receding chin, Hauber developed a plan for accomplishment of normal features. He left Loras College in Dubuque, where he had been enrolled two years studying for Catholic priesthood, to build a bank account for the surgery.

Studies Languages

Surgeons have assured Hauber that a series of operations would be necessary. The surgery will be expensive. When Charles has saved $1,000, he’ll submit himslef for the initial work. The accumulation of savings is slow–but Hauber already has more than $400 in the bank.

Hauber is a most unusual construction timekeeper. He has had three years of Greek and four years of Latin. He has had three years of German and a year of French. He even has had six months of Spanish.

Besides his interest in languages, Hauber is an enthusiastic amateur short story writer. He has written several stories–without ever submitting any to editors for professional judgment. And, as a student of people and human nature, he’s constantly alert for character studies and incidents he can incorporate in fiction writing.

Worked on Elevators

Eldest of six children of Mr. and Mrs. Carl Hauber of Emmetsburg, Charles–known to co-workers as “Chuck”–for two years attended a Catholic seminary at East Troy, Wis., a school conducted by the Society of Divine Word. He also had a year at Epworth College, near Dubuque.

When Hauber first was employed by the Tillotson Construction Co. of Omaha, he worked on an elevator project at Bancroft. Then the crew shifted to the Farmer’s Elevator Co. at Ralston. After a “repair job” at Aurora, Neb., he was assigned to the elevator construction project at Boxholm.

Here the Tillotson company is building the $151,000 addition on the Farmer’s Co-Operative Co. elevator.

Hauber likes his work–but his dreams go beyond a career in construction business. Whether he’ll return to studies for the priesthood, he hasn’t determined. His interest in languages–which he continues to study after working hours–has kindled thoughts of becoming an interpreter. Possibilities as a writer are not overlooked.

Whatever he heads for, be assured Hauber will give it the old college try–and he hopes to have “a determined chin” to show with it.

Tillotson Construction Co. wins $110,500 contract for large storage annex at Gurley, Neb.

More Grain Storage Seen

By the Associated Press, Friday, April 25, 1958

Commercial grain storage in Cheyenne County will be more than half million bushels larger for the 1958 crops than was available last year.

The Farmers Union Co-op Grain Co. of Gurley has let a contract for the construction of 8 cement tank-type grain storage bins.

Ross Handley, president of the co-op board of directors, said a contract for $110,500 was let to Tillotson Construction Co. of Omaha.

Arnold Draper of Gurley, member of the board of directors, reported that this new addition will add 274,000 bushels in grain storage to the present plant.

Plans call for placing this year’s crop of wheat in the new tanks.

Work is also under way at Dalton and about 20 miles north of Sidney for the Dalton Co-op Society to add some 250,000 bushels of storage to its facilities.

Farmers Union Grain Co. of Sidney plans to have about 70,000 bushels of additional space ready for the 1958 harvest.

The added storage will be urgently needed if present winter wheat prospects materialize into a big harvest.

Estimates now call for a harvest from the Panhandle of 20 to 25 million bushels of wheat this crop year.

We thank our friend Susan Allen for unearthing this and other clippings.

Fragmentary biography of Tillotson Construction Co. employee Charles Hauber in 1955

From the Des Moines Tribune, Friday, Dec. 16, 1955:

Worked On Elevators

Eldest of six children of Mr. and Mrs. Carl Hauber of Emmetsburg, Charles–known to co-workers as “Chuck”–for two years attended a Catholic seminary at East Troy, Wes., a school conducted by the Society of the Divine Word.

He also had a year at Epworth College, near Dubuque.

When Hauber first was employed by the Tillotson Construction Co. of Omaha, he worked on an elevator project at Bancroft. Then the crew shifted to the Farmer’s Elevator Co. at …

An Iowa company built an elevator in Ceresco, Neb., imitating Tillotson’s style

For a small eastern Nebraska town, Ceresco is well-known within its region because of a furniture store, Ernie’s in Ceresco, that advertises widely.

When Kate Oshima visited Ernie’s to look for bargains, she happened to notice a handsome grain elevator with a curved headhouse.

At first we wondered if this was an unrecorded project by Tillotson Construction Co.

But Kate got a photo of a manhole cover that tells otherwise: Grain Storage Construction Co., of Council Bluffs, Iowa, takes credit for the 1959 job.

We find no background information on this company.

But the curved headhouse makes us wonder if Tillotson design talent migrated across the Missouri River to Omaha’s twin city and worked there.

Tillotson’s construction record ends at 1955. From the accompanying photos taken by Kate, this elevator’s style sure looks familiar.