Rain delays and balky formwork hindered Grain Storage Construction Co. at Ceresco, Neb.

Lincoln Journal Star, Friday, Sep. 18, 1959

Grain Storage Construction Co. benefited from the expertise of Ted Morris, who had been employed by Tillotson Construction Co. As Tillotson’s activities declined in the late-1950s, the GSCC, of Council Bluffs, Iowa, stepped in to undertake construction of new grain elevators.

Here is news from the Fremont (Neb.) Tribune on July 24, 1959 as the company’s crew built an elevator of reinforced concrete next to a traditional wooden elevator at Ceresco, a village just 20 miles north of the Nebraska Capitol building in downtown Lincoln.

Weather, Difficulties Delay Bin Construction at Ceresco

CERESCO–The Farmers Cooperative Association’s new, 250,000-bushel capacity grain elevator being constructed here by Grain Storage Const. Co. of Council Bluffs, Iowa, is expected to be completed by Sept. 1, according to project foreman Doyle Elliott.

The elevator will have 120-foot high storage tanks, topped by a 42 1/2-foot scale house. Tank construction is one third complete.

* * *

Construction of the new elevator started April 1, but work progress was hampered by a lengthy rain spell during the initial weeks. Difficulty with the hydraulic hoists, which raise the movable wood form after concrete has been poured, caused a brief shutdown of pouring operations.

The wood frame held too tightly in some places and left a few unfilled pockets in the concrete shell of the storage tank walls. Construction workers are patching up the pockets and new concrete pouring should begin sometime next week.

Once the pouring begins the tank walls can be built up at the rate of 16 feet every 24 hours. “Most people judge progress in elevator construction by the outside appearance,” said Elliott. “They do not realize how much inside work has to be accomplished before you can proceed safely with the exterior work,” he added.

“We hope the elevator will be ready by Sept. 1,” said Farmers Co-op Assn. manager Leonard Palm. “We would like to get this year’s corn crop in. I think we will make it as there have been no serious construction flaws or delays so far,” he added. 

Editor’s note: Based on the Sep. 18, 1959 date of the Lincoln Journal Star’s photo and caption (top), GSCC did not manage to complete the elevator by the date the Co-op had hoped for.

We thank our friend Susan Allen for unearthing the clippings.

Tillotson Construction Co. alumnus Ted Morris leads new elevator job at Beatrice, Neb. in 1958

Beatrice (Neb.) Daily Sun, Oct. 28, 1958

The contract to build the 100,000 bushel elevator on the old Wiebe Lumber Co. property has already been let, August Grell said last night. He stated that the contractor is Ted Morris, Grain Storage Construction Co., Council Bluffs, Ia. They have materials on order and are ready to go to work, he stated. The Beatrice Concrete Co. has a sub-contract for furnishing the concrete for the structure, which is to be built at an estimated cost of $250,000.

Editor’s note: There is a discrepancy in capacity of the elevator as recorded in the two articles. We believe the 340,000-bushel figure is more likely correct.

The Lincoln Star, Dec. 27, 1958

Beatrice, Neb. — Construction has begun here on a new 340,000 bushel capacity grain elevator by the Farmer’s Co-Op. Being built by the Grain Storage Construction Co. of Council Bluffs, Ia., the elevator will consist of 8 concrete bins, 120 feet high with a 40-foot high headhouse on top to house lifting machinery.

We thank our friend Susan Allen for unearthing this and other clippings.

 

Beatrice Daily Sun, Dec. 26, 1958