Tillotson Construction completes Big Springs sorghum plant

Photo courtesy of Farmers Elevator Coop Association

BIG SPRINGS–The Tillotson Construction Co., Hastings, Neb., has completed a $40,000 building for the Farmers Cooperative Elevator sorghum plant.

Farmers’ Elevator Guide, August 1951

Note: A conversation today with Larry McCroden, long-time manager of the Big Springs Farmers Coop Elevator, reveals additional information about the facilities. Mr. McCroden consulted tax documents that showed “Elevator A” had a value of $184,432 and “Elevator B” had a value of $25,100. He said the twenty original bins of Elevator A stand about 115 feet tall, and the two-tiered headhouse reaches to 170 feet. The documents give January 15, 1951 as the date of service for the two.

Later additions were made to the original structure, increasing storage capacity by hundreds of thousands of bushels.

Mr. MrCroden said the elevator at Roggen, Colorado, bears many similarities to Big Springs.

Additional note: We don’t know why Hastings, Nebraska is given as the location of Tillotson Construction Co., which had its headquarters in Omaha.

Tillotson gets 50,000-bushel Paullina elevator under way

Paullina elevator complex, Dec. 9, 2009, by Jim Hamann

PAULLINA (IOWA)–A new concrete elevator is under construction to replace the Paullina Grain Co. elevator destroyed by fire. The new one will be 103 feet high, containing 18 bins. All new machinery, including a 50-ton scale, will be installed. Capacity will be 50,000 bushels.

Farmers’ Elevator Guide, June 1949

One of Tillotson’s biggest elevators under way in Dallas Center

Photo by Don McLaughlin on April 11, 2010. Click on the photo to visit his photostream.

DALLAS CENTER–Work has started on a 250,000-bushel concrete elevator for Dallas Center Farmers Cooperative Company. It will be 166 feet tall and is being built by Tillotson Construction Company at a cost of $151,000.

Located west of the firm’s south elevator, it is 56×70 in base dimensions.

Aeration equipment will be included in each of the ten 23,000-bushel bins, Manager Don Brown reports.

Farmers’ Elevator Guide, circa September 1955

Dallas Center

Photo by Pete Zarria, April 1, 2011. Click the image to visit his photostream.

See another recent images from Dallas Center: 

January 7, 2012

This map shows the incorporated and unincorpor...

Boxholm manager foresees timely completion of Tillotson’s new elevator

Photo uploaded to KCCI in 2009 by the station's u local contributor hmuench

Boxholm, Iowa–Manager Bud Lane reported that the new 200,000-bushel Farmers Cooperative Elevator Company’s concrete elevator will be completed on July 15. Tillotson Construction Co. of Omaha is the builder.

The structure will rise 150 feet with storage tanks standing 120 feet high.

The firm will have 256,000 bushels of space with the new unit.

Farmers’ Elevator Guide, 1954-1955 library volume 

♦ ♦ ♦

Note: The Boxholm Farmer’s elevator was founded in 1900, according to a 2004 article in the Dayton Review. On October 25, 2004, the elevator–now expanded–took in 145,422 bushels of grain, the new single-day record at this location. For the entire 2004 harvest season, more than 2 million bushes were taken in.

On November 16, 2009, two workers were injured when a grain dryer exploded at the Boxholm elevator. See the report from Des Moines station KCCI.

This map shows the incorporated and unincorpor...

Boxholm is in northwestern Boone County, Iowa.

Kristen’s visit to her grandfather’s elevator in Blencoe, Iowa

Story and photos by Kristen Osborn Cart

When I was out to Nebraska with the kids to see my Mom and Dad in 2011, we took the long way home to Illinois and stopped at Blencoe, Iowa, to see the grain elevator.

Dad helped to build it with Grandpa and Mayer-Osborn Company in the summer of 1954, just as he was starting his last year of college.

Blencoe is a tiny Monona County town of  about 200 people. It’s just off Interstate 29, halfway between Council Bluffs and Sioux City.

In March of 1954 Mayer-Osborn won the contract from Blencoe Co-operative Company, worth $153,000, to build the 259,000-bushel facility. It featured a stepped, rounded headhouse.

Dad and his brother Dick laid the rebar during the concrete pour as the elevator went up. Dad had to go back to school before construction was finished because football practice was getting under way.

On my visit, I stopped at the office, where they had a notebook with the fifty-year history of the cooperative. They were proud of their elevators at Blencoe, and the folks there showed me around.  

This elevator is very similar to the elevator Grandpa built in McCook, Nebraska.

Tillotson Construction hurries to meet deadline in Aurora, Nebraska

Photo by David Wilson

Contracts for new elevators at Aurora and Murphy were let by the Aurora Cooperative Elevator Co. The Aurora 250,000-bushel concrete elevator will be built by Tillotson Construction Co. of Omaha. The 33,000-bushel plant at Murphy will be erected by Black, Sivalls & Bryson, Kansas City, Mo., bolted steel tank construction company. The cooperative has a government contract to store grains for three years and the elevators must be completed by September 15 to meet terms of the contracts. The Murphy elevator will be in use by mid-July.

Farmers’ Elevator Guide, July 1950 

By January of 1955, it was reported that the co-op was operating a new, 271,000-bushel addition built by Tillotson, bringing overall capacity to 551,000 bushels.

Related articles

Farmers’ Elevator Guide reports Tillotson Construction’s record Montevideo project

The following story and photos are reproduced from library copies of the January 1950 edition of Farmers’ Elevator Guide:

Complete Service: Minnesota Equity Elevator Builds to Fill Area Needs

Tillotson Construction's Bill Russell, far right, instructs (from left) Stanley Kittleson, Adrian Dahl, and Merlynn Nelson on operation of the elevator's distributor controls.

Moving quickly to establish itself as the principal district elevator for grain handling, the Farmers Equity Elevator Co. of Montivideo, Minn., has a new 100,000-bushel capacity concrete elevator in full operation after a whirlwind effort to get it built to meet needs of the fall harvest.

When it became apparent that existing facilities in the area left room for a vast expansion to handle grain crops, the Farmers Equity Elevator Company decided to expand its plant which had only 25,000 bushels of capacity.

The project, begun late in August, was rushed to completion by Tillotson Construction Co. of Omaha, Neb, in record time. Concrete pouring by round-the-clock crews was completed in nine days and four hours. This bettered by 18 hours any previous accomplishment for an elevator of this size.

The structure is 102 feet high and has a cupola 29 feet high. It has 17 bins.

Installed during erection was a $15,000 corn drying plant and, on the midway level, a $10,000 grain cleaning installation. This included a large Crippin sieve machine, a large Superior cleaner, a Slurry grain treater and other equipment.

The new building houses a weighing and sampling room but the offices of the company are in the old quarters.

Sliding tubular forms were used to permit the rapid construction.

The plant cost $120,000 including $10,000 for piling costs, but other equipment raised the total to $134,000. Features include a 50-ton, 50-foot long scale with lighted dial and printomatic type registering beam. It has two concrete elevating legs each with 30 h.p. head drive and elevating capacity of 5,000 bushels per hour dumping into a Gerber distributing system. Its dump pit has two sections each built under the driveway and extending 12 feet below ground. All bins are hoppered to discharge into pit.

Two large cleaners installed are a Superior cylinder subterminal size machine for coarse grains and a Crippin screen cleaner for flax. All grains will be commercially cleaned before loading out to add profit to operations. The mills can be adjusted for farm seed cleaning in spring months. Gravity is used to feed mills from above and to distribute grain into bins below before loading to cars.

A 400-bushels-per-hour new type Campbell corn dryer was installed at a cost of $15,000. Some 50,000 bushels of the government loan 1949 corn crop were taken in and dried.

The new elevator was dedicated Dec. 29 with President J.W. Evans, also president of the American Soybean Association, presiding.

In 1945, William Osborn worked on Tillotson Construction’s elevator in Giddings, Texas

Map of Texas highlighting Lee CountyThis elevator at Giddings, Texas, called the Fairmont Building, is the only one I have pictures for that my grandfather built when he worked for Tillotson Construction Company of Omaha. It would have been built in 1944 and 1945, when my dad turned eleven years old. Dad went to visit my grandpa William Osborn at Galveston in the spring of 1945 during this project. — Kristen

Note: Nutrena bought Fairmont Foods’ plant in Giddings in 1955.

Open house to welcome Tillotson Construction’s large elevator at Rock Valley


Photo by Rock Valley city administrator Tom Van Maanen

Rock Valley, Iowa–In June 1950, Farmers’ Elevator Guide reported a 270,000-bushel, $125,000 concrete grain storage elevator was being put up by Farmers Elevator Company.

In November the same publication reported an October 7 open house at the facility. Final cost and capacity were $150,000 and 310,000 bushels. This was “said to be the second largest in the northwest section of Iowa.”

Other key dimensions:

  • A footprint of 65 by 85 feet
  • Height: 160 feet
  • 34 bins ranging from 300 bushels to 28,000 in capacity

Features included a “cleaner room” and a grain dryer adjacent to the elevator.

Tillotson Construction Company, of Omaha, contracted the work.

Men wanted in Paullina, Iowa, by Tillotson Construction in 1949

Back Alley, Paullina, Iowa, by Jim Hamann

MEN WANTED for construction work on Concrete Grain Elevator, 90¢ per hour, 10 hours a day, 6 and 7 days a week. Time and ½ over 40 hours.

Tillotson Const Co. at Paullina, Ia.

The Alton, Iowa Democrat, Thursday, May 5, 1949

Editor’s note: In 2008, an explosion and fire injured a customer at the new elevator in Alton.

This map shows the incorporated and unincorpor...

Image via Wikipedia