The Tillotson elevator in Boxholm, Iowa, afforded unique photographic possibilities

DSC_0535Story and photos by Kristen Cart

The Boxholm elevator located in central Iowa was an intriguing destination, particularly since I had knowingly passed it by, missing it by a few miles on more than one trip. It became imperative to make the detour to see it. I was glad I did, since the elevator made beautiful pictures on that early summer day. I used a wide-angle lens that added pronounced distortion to the scene, causing the buildings on the edges to lean in dramatically. But the leaning lines pointed to the beautifully clouded sky.

You can use a wide-angle lens to include more of the scene from close quarters than would be possible with another lens, but you forfeit realism. This is not a problem for certain artistic photos, but it is not ideal for documentary shots. When photographing buildings where you want to preserve parallel lines, you must stand farther away and use a longer focal-length lens. At Boxholm, I did not have that option.

DSC_0547

Wide-angle lens distortion is maximized in this view.

At extremely close quarters, the wide-angle lens exaggerates height and adds drama. But the distortion becomes more pronounced.

The Tillotson Construction Company of Omaha, Neb., built the elevator in 1955. An annex stands beside it, and an old wooden feed mill is beside that. A much newer elevator with the West Central logo was built later, after it became customary to leave the concrete plain, without the white finish.

DSC_0563

A more conventional view of the elevator complex.

The specifications for the Boxholm elevator are among the Tillotson Company construction records. We learned some details about the elevator from a few stray sources before my visit; for instance, the elevator has exactly 96 light bulbs installed. Its construction followed the Drummond plan. Other projects using the same architectural plan were the elevators at Waverly, Neb., and Lahoma and Drummond, Okla.

Specifications

Capacity per plans (with Dock): 199,400 bushels

Capacity per foot of height: 2,002 bushels

Reinforced concrete per plans (total): 1,797 cubic yards

Plain concrete (3″ hoppers): 33 cubic yards

Reinforcing steel per plans (includes jack rods): 85.71 tons

Average steel per cubic yard reinforced concrete: 95.4 pounds

Steel and reinforced concrete itemized per plans:

Below main slab: 6,861 pounds steel, 59.2 cubic yards concrete

Main slab: 25,603 pounds steel, 202 cubic yards concrete

Drawform walls: 103,192 pounds steel, 1,295 cubic yards concrete

Driveway and Work floor : 3,820 pounds steel, 23.8 cubic yards concrete

Deep bin bottoms (including columns): 7,271 pounds steel, 39.3 cubic yards concrete

Overhead Bin bottoms: 6,040 pounds steel, 27.6 cubic yards concrete

Bin roof and Extension Roofs: 7,210 pounds steel, 41.7 cubic yards concrete

Scale floor (or garner complete): 160 pounds steel, 2.5 cubic yards concrete

Cupola walls (including leg & head): 7,257 pounds steel, 76 cubic yards concrete

Distributor floor: 1,560 pound steel, 9.4 cubic yards concrete

Cupola roof: 2,147 pounds steel, 15.6 cubic yards concrete

Misc. (track sink, steps, etc.): 173 pounds steel, 3.5 cubic yards concrete

Attached driveway: none

Bridge and/or Tunnel: none

Pit Liner–plain: 16 cubic yards concrete

Drier Bin Bottom: 134 pounds steel, 1.3 cubic yards concrete

Coffer Dam, Cleaner Floor: Wood

Remarks: 10 Bin Hot spot; 8 Bin Aeration tubes; Dryer bin

DSC_0541

The rounded headhouse is a reliable indicator of a Tillotson elevator

Construction details

Like Waverly: construction details were identical to Waverly and not listed separately in the records.

Main slab dimensions (drive length first dimension): 56 1/2′ x 70′

Main slab area (actual outside on ground): 3,850 square feet

Weight reinforced (total) concrete (4000 pounds per cubic yard plus steel): 3,747 tons

Weight plain concrete (hoppers; 4000 pounds per cubic yard): 98 tons

Weight hopper fill sand (3000 pounds per cubic yard): 732 tons

Weight of grain (at 60 pounds per bushel): 5,982 tons

Weight of structural steel and machinery: 20 tons

Gross weight loaded: 10,579 tons

Bearing pressure: 2.75 tons per square foot

Main slab thickness: 24″ with 3″ pile cap

Main slab steel: straight #9 at 7″ spacing

Tank steel and bottom (round tanks): #4 at 12″ spacing

Lineal feet of drawform walls & extension: 606′

Height of drawform walls: 120′

Pit depth below main slab: 15’3″

Cupola dimensions (outside width x length x height): 22 1/4′ x 48 1/2′ x 35′

Pulley centers: 160.75′

Number of legs: 1

Distributor floor: yes

Track sink: yes

Full basement: yes

Electrical room: yes

Driveway width clear: 13′

Dump grate size: 2 at 9′ x 5′ and 9′ x 15′

Column under tanks size: 16″ square

Boot legs and head: concrete

DSC_0531Machinery details

Boot pulley: 72″ x 14″ x 4 15/16″

Head pulley: 72″ x 14″ x 2 7/16″

R.P.M. Head pulley: 42

Belt: 335′, 14″ 6 ply Calumet

Cups: 12″ x 6″ at 8″ spacing

Head drive: Howell 40 horsepower [4 circled here]

Theoretical leg capacity (cup manufacturers rating): 8,440 bushels per hour

Actual leg capacity (80% of theoretical rating): 6,750 bushels per hour

Horsepower required for leg (based on actual capacity): 32 horsepower

Man lift: 1 1/2 horsepower Ehr.

Load out scale: 25 Bushel

Load out spout: 10″ diameter

Truck lift: 7 1/2 horsepower Ehr.

Dust collector system: Fan to bin

Cupola spouting: 10″ diameter

Driveway doors: 2 overhead rolling

Conveyor: provision

Remarks

see page 10 (above)

A Tillotson skyscraper dominates corn country in Randall, Iowa

DSC_0638

Story and photos by Kristen Cart

During every elevator scouting trip, there comes a fork in the road where we choose which elevator to see, and which to save for another time. On the way home from Nebraska this summer we came to such a place at the junction of Iowa Route 175 and US 69 in central Iowa. To the north I could see the silhouette of an elevator at Jewell, and just east from Jewell, across the South Skunk River, the town of Ellsworth beckoned. But as I checked my map, to the south I saw Randall, which was a familiar name. I elected to turn south onto US 69.

The name should have been familiar, because it is found in several places in the Tillotson Construction Company records. The elevator in the central Iowa town of Randall was built in 1949 using the “Dike Plan.”

DSC_0662

The elevator commands the Randall skyline

In the company records for subsequent projects at West Bend and Pocahontas, Iowa, both built using the Dike plan, the quantities of concrete and steel and the machinery details were summarized with the shorthand, “Like Randall,” for each project. The Dike plan was widely used for Tillotson’s quarter-million-bushel elevators.

The Randall elevator and its annexes overlooked a silent street of empty storefronts on that quiet Sunday. The co-op office looked new and efficient. The town was a perfect snapshot of the principle of economy-of-scale: the small business, like the small farm operation, must grow, combine forces, or die.

We have the construction records for Randall’s elevator and its siblings in West Bend and Pocahontas, which vary in minor details. Randall’s specifications follow.

DSC_0644

The Randall Lumber Co. appears to be a survivor of the economic slump.

 

Specifications

Capacity per plans (with Dock): 252,000 bushels

Capacity per foot of height: 2,520 bushels

Reinforced concrete per plans (total): 2,066 cubic yards

Plain concrete (hoppers): 40 cubic yards

Reinforcing steel per plans (including jack rods): 109.37 tons

Average steel per cubic yard reinforced concrete: 106 pounds

Steel and reinforced concrete itemized per plans:

Below main slab: 4,637 pounds steel, 40 cubic yards concrete

Main slab: 39,291 pounds steel, 266 cubic yards concrete

Drawform walls: 129,000 pounds steel, 1,430 cubic yards concrete

Work and Driveway floor (including columns): 3,700 pounds steel, 24 cubic yards concrete

Deep bin bottoms: 11,832 pounds steel, 58 cubic yards concrete

Overhead Bin bottoms: 4,876 pounds concrete, 30 cubic yards concrete

Bin roof (or garner): 8,791 pounds steel, 56 cubic yards concrete

Scale floor (complete): none

Cupola walls: 8,404 pounds steel, 92 cubic yards concrete

Distributor floor: 1,848 pound steel, 11 cubic yards concrete

Cupola roof: 2,360 pounds steel, 18 cubic yards concrete

Misc. (boot, leg, head, track sink, steps, etc.): 3,000 pounds steel, 30 cubic yards concrete

Attached driveway: 1000 pounds steel, 11 cubic yards concrete (driveway extension, walls and roof)

DSC_0664Construction details

Main slab dimensions (drive length first dimension): 60′ x 72 1/2′

Main slab area (actual outside on ground): 4,200 square feet

Weight reinforced (total) concrete (4000 pounds per cubic yard plus steel): 4,241 tons

Weight plain concrete (hoppers 4000 pounds per cubic yard): 74 tons

Weight hopper fill sand (3000 pounds per cubic yard): 985 tons

Weight of grain (at 60 pounds per bushel): 7,560 tons

Weight of structural steel and machinery: 20 tons

Gross weight loaded: 12,880 tons

Bearing pressure: 3.06 tons per square foot

Main slab thickness: 21″

Main slab steel: bent 1″ square at 7″ o. c. spacing

Tank steel and bottom (round tanks): 1/2″ diameter at 9″ o. c. spacing

Lineal feet of drawform walls: 655 excluding extension

Height of drawform walls: 120′

Pit depth below main slab: 14’9″

Cupola dimensions (outside width x length x height): 24 1/2′ x 50 1/4′ x 40′

Pulley centers: 165.25′

Number of legs: 1

Distributor floor: yes

Track sink: yes

Full basement: yes

Electrical room: yes

Driveway width clear: 12′

Dump grate size: 2 at 9′ x 6′ and 9′ x 14′

Column under tanks size: 20″ square

Boot legs and head: concrete

DSC_0635Machinery details

Boot pulley: 72″ x 14″ x 2 3/16″

Head pulley: 72″ x 14″ x 3 15/16″

R.P.M. Head pulley: 42

Belt: 355′, 14″ 6 ply Calumet

Cups: 12″ x 6″ at 8 1/2″ o. c. spacing

Head drive: Howell 40 horsepower [3 circled here]

Theoretical leg capacity (cup manufacturers rating): 7,920 bushels per hour

Actual leg capacity (80% of theoretical rating): 6,340 bushels per hour

Horsepower required for leg (based on above actual capacity plus 15% for motor): 32 horsepower

Man lift: 2 horsepower Ehr.

Load out scale: 10 Bu. Rich.

Load out spout: 10″ w.c.

Cupola spouting: 10″ diameter 14 gauge

Truck lift: 7 1/2 horsepower Ehr.

Dust collector system: Fan to bin

Driveway doors: 2 overhead rolling

Conveyor: provision

Remarks

3 bin distributor under scale

Provision for hopper scale

 

 

 

 

The twin of the vanished Glidden, Iowa, elevator still stands at Churdan, Iowa

DSC_0476Story and photos by Kristen Cart

Tucked into a nest of grain bins in the west-central Iowa town of Churdan is an old original elevator built by Tillotson Construction Company of Omaha, Neb. The annex hard by its side also boasts the Tillotson name.

DSC_0454

It is immediately obvious that the old Tillotson structure has been updated at some time in the past with a leg that extends above the headhouse, thereby keeping the machinery most prone to overheating far from accumulations of grain dust.

DSC_0497DSC_0490The annex beside it shows signs of cracking. Stress cracks are an old enemy of elevators, a problem which eventually spelled the demise of the Churdan elevator’s twin at Glidden, Iowa, and also the Mayer-Osborn elevator at Maywood, Kan.

Manhole covers along the side declare that the annex was built by Tillotson Construction in 1955.

DSC_0486An elevator built by Quad States was added to the Farmers Cooperative complex some years later. (Its trademark stepped headhouse is curved only at the outside margins, a usually reliable indicator of a Quad States design. A manhole cover dated 1969 boasts its provenance.)

A white-painted metal bin, served by the Tillotson elevator headhouse, was also added to the site to increase storage capacity.

DSC_0463

Click the photo to witness the demolition

After demolition of two faulty bins in 2013, the concrete remnants were bulldozed into the center of an empty lot across from the co-op office.

A large-capacity shiny metal bin across the street completes the scene.

We are fortunate to have the specifications for the Churdan elevator, which is an early example built in 1949, and for its 198,960-bushel annex. The elevator specifications are detailed below.

The “Churdan Plan” was used for a number of Tillotson elevators, including Glidden, Sanborn, Gilmore City, and Thompson, Iowa; Greenwood and Fairfield, Neb.; and Montevideo, Minn. The construction of elevators using this plan spanned from 1949 to 1952. Specifications varied according to an individual customer’s  requirements.

The “Churdan Plan” consisted of four 14 1/2-foot-diameter bins, 100 feet tall, with a 13-by-17-foot driveway and eight bins over the driveway. It had a 13-foot spread. Notations in the company record said “bin split for drier” and “16 bins and dust bin.”

Specifications

Capacity per plans (with Dock): 102,000 bushels

Capacity per foot of height: 1,318 bushels

Reinforced concrete per plans (total): 1,083 cubic yards

Plain concrete (hoppers): 25 cubic yards

Reinforcing steel per plans (including jack rods): 57.72 tons

Average steel per cubic yard reinforced concrete: 106.5 pounds

Steel and reinforced concrete itemized per plans:

Below main slab: 3,133 pounds steel, 29 cubic yards concrete

Main slab: 15,937 pounds steel, 113 cubic yards concrete

Drawform walls: 73,405 pounds steel, 760 cubic yards concrete

Work and Driveway floor (including columns): 3,370 pounds steel, 26 cubic yards concrete

Deep bin bottoms: 3,480 pounds steel, 19 cubic yards concrete

Overhead Bin bottoms: 3,752 pounds concrete, 23 cubic yards concrete

Bin roof (or garner): 3,060 pounds steel, 30 cubic yards concrete

Scale floor (complete): 186 pounds steel, 3 cubic yards concrete

Cupola walls: 3,481 pounds steel, 35 cubic yards concrete

Distributor floor: 886 pound steel, 7 cubic yards concrete

Cupola roof: 1,129 pounds steel, 9 cubic yards concrete

Misc. (boot, leg, head, track sink, steps, etc.): 1,036 pounds steel, 20 cubic yards concrete

Attached driveway: 600 pounds steel, 9 cubic yards concrete (driveway extension)

DSC_0494Construction details

Main slab dimensions (drive length first dimension): 48′ x 48′

Main slab area (actual outside on ground): 2,270 square feet

Weight reinforced (total) concrete (4000 pounds per cubic yard plus steel): 2,224 tons

Weight plain concrete (hoppers 4000 pounds per cubic yard): 50 tons

Weight hopper fill sand (3000 pounds per cubic yard): 360 tons

Weight of grain (at 60 pounds per bushel): 3,060 tons

Weight of structural steel and machinery: 15 tons

Gross weight loaded: 5,709 tons

Bearing pressure: 2.52 tons per square foot

Main slab thickness: 18″

Main slab steel: straight 1 1/4″ square at 10″ o. c. spacing

Tank steel and bottom (round tanks): 3/8″ at 8″ o. c. spacing

Lineal feet of drawform walls: 440 excluding extension

Height of drawform walls: 90′

Pit depth below main slab: 12’0″

Cupola dimensions (outside width x length x height): 15′ x 32 1/3′ x 22′

Pulley centers: 115.67′

Number of legs: 1

Distributor floor: yes

Track sink: yes

Full basement: yes

Electrical room: yes

Driveway width clear: 13′

Dump grate size: 2 at 9′ x 5 1/2′ and 9′ x 15′

Column under tanks size: 16″ square

Boot legs and head: concrete

Machinery details

Boot pulley: 60″ x 14″ x 2 3/16″

Head pulley: 60″ x 14″ x 3 15/16″

R.P.M. Head pulley: 44

Belt: 272′, 14″ 6 ply Calumet

Cups: 12″ x 6″ at 9″ o. c. spacing

Head drive: Howell 30 horsepower [3 circled here]

Theoretical leg capacity (cup manufacturers rating): 6,540 bushels per hour

Actual leg capacity (80% of theoretical rating): 5,230 bushels per hour

Horsepower required for leg (based on above actual capacity plus 15% for motor): 19.9 horsepower

Man lift: 2 horsepower Ehr.

Load out scale: 10 Bu. Rich.

Load out spout: 8 1/4″ w.c.

Cupola spouting: 10″ diameter 14 ga.

Truck lift: 7 1/2 horsepower Ehr.

Dust collector system: Fan to bin

Driveway doors: 2 overhead rolling

Conveyor: None

Remarks

Split bin for dryer

A last farewell to the Tillotson terminal elevator art works on Vinton Street

DSC_0372Story and photos by Kristen Cart

In the last weeks, the unique art project along I-80 in Omaha, Neb., came down as the Vinton Street display was concluded. The Tillotson Construction elevator stands now as it always did, plain and utilitarian, while still graceful in its own way.

As the Vinton Street banners first went up in the two phases of Emerging Terrain’s Stored Potential, first in 2010 and then in 2012, I had the opportunity to visit and photograph them. They had not weathered harsh winters and hard sunlight yet, and were as bright as the artists’ fresh paint.

Here are a few images, as a last tribute to this unique community art project.

The beauty of this project speaks for itself. The elevator now stands denuded of its decoration, yet poised for the next phase of its long and useful life.

DSC_0394

DSC_0397DSC_0443

DSC_0382

A Tillotson elevator overlooks the 76th Dayton Championship Rodeo grounds

DSC_0591

The Dayton, Iowa, rodeo grounds bustle with activity for the championship event.

Story and photos by Kristen Cart

The Dayton, Iowa, elevator is an especially handsome one, built in a typical Tillotson style. It is one of an overwhelming majority of Tillotson elevators that are still in use. It is quite an achievement to build something so enduring.

DSC_0566

Modern updates are evident in this view.

One of the secrets of the longevity of concrete elevators of this type is the ability to upgrade the machinery and to expand capacity. The elevators were built with the understanding that they would soon be filled and would need additional bins. The Tillotson Construction Company revisited certain sites over and over as they added concrete annexes and other improvements, while occasionally other companies won the contracts.

DSC_0579

The feed mill stands to the right.

You can see that the concrete elevator was retrofitted with an external leg. This modification is a safer design than the old internal one, because accumulated grain dust cannot come into contact with overheated machinery if a bearing or belt fails. Metal bins were added for additional capacity. A feed mill complements the storage facility, completing a one-stop shop for farmers.

The Dayton elevator’s original construction was not without trouble, however. Tillotson Construction Company was compelled to pay for repairs after the elevator cracked under its original grain load. The Farmers Elevator Company sued, according to the Farmers Elevator Guide, in 1954. The repairs were expertly done and the elevator still stands today.

The elevator and its Tillotson annex preside in sleepy Dike, Iowa

The old elevator sits beside its wooden predecessor, as it did in 1946

The old elevator sits beside a wooden elevator, as it did in 1946

Story and photos by Kristen Cart

We took a number of elevator detours on our return home from a Nebraska trip, where we delivered our daughter to her summer veterinary camp. During the four-day program presented by Oxbow Animal Health, she learned the inner workings of a cow, and lovingly operated on and sutured a stuffed bunny. Apparently there is no such experience offered to children in Illinois.

The trip home was a meandering route with a number of switchbacks, with elevators built by Tillotson Construction, of Omaha, spaced every few miles. One elevator stop on our sojourn was Dike, Iowa, in the central part of the state. This fascinating site was the last one we saw before the light failed. We were racing a line of weather, and as the sun sank the clouds built and made for very flat light.

DSC_0721It is enlightening to see an elevator complex in person and compare it with an early photograph. The changes wrought in almost seventy years can be surprising, but even more unexpected can be the features that remain the same.

At Dike, you immediately notice a wooden structure behind the main structure. Strangely, it does not appear to be the same elevator that appears in the old photograph. Why would the co-op replace a wooden elevator with another one? The obvious answer would be a fire, but if wood was obsolete, why continue to build with that material?

In my travels, I have rarely come across a wooden elevator that was built before the 1940s and still in use today. Technology rendered the old ones obsolete, and wear and tear made them difficult to operate. Fire also took many of them. Now, wooden elevators built as late as the 1970s are coming down as more valuable uses are found for their wood, and as regulations make them harder to license.

The main house of Tillotson Construction's elevator at Dike, Iowa, built in 1946 (annex, left, 1949), is crowned by a rectilinear headhouse.

The main house of the elevator at Dike, Iowa, built in 1946 (Tillotson Construction’s annex, left, 1949), is crowned by a rectilinear headhouse.

Dike’s concrete elevator was built in 1946, and it came with an unusual (for Tillotson) headhouse. In the one place where we found a similar example, at St. Francis, Kan., the elevator built by J. H. Tillotson, Contractor, sported a rectilinear headhouse. Though it was replaced much later, early pictures show that the St. Francis headhouse was built in that style.

Both the old Omaha company and its later offshoots preferred curved architecture because it was more economical to build.

So the Dike elevator was a non-typical construction, and we know from its early photo that it started out that way. Since we have no record of it in our Tillotson company records, we have to assume it was built by another company. But the Omaha company led by Reginald Tillotson built the annex.

DSC_0702Tillotson Construction arrived on scene in 1949 to add the annex just three years after the main house was built. In the late 1940s, when elevators were filled just as fast as they could be built, annexes sprung up almost before the concrete cured on the original elevators.

The Dike, Iowa, annex specifications

Capacity per plans (with pack): 200,700 bushels

Capacity per foot of height: 1,859

Reinforced concrete per plans (total): 1,255 cubic yards

Plain concrete (hoppers): 3 cubic yards

Reinforcing steel (including jack rods): 73.56 tons

Average steel per cubic yard of concrete: 117.2 pounds

Steel and reinforced concrete per plans:

Below main slab: None

Main slab: 23,665 pounds steel and 218 cubic yards concrete

Drawform walls: 94,152 pounds steel and 880 cubic yards concrete

Work and drying floor: None

Deep bin bottoms: None

Overhead bin bottoms: 18,156 pounds steel and 56 cubic yards concrete

Bin roof: 4,223 pounds steel and 32 cubic yards concrete

Scale floor: None

Distributor floor: 3,570 pounds steel and 30 cubic yards concrete

Cupola roof: Steel included in above amount, and 21 cubic yards concrete

Misc. (Boot, leg, head, track sink, steps, etc.): 500 pounds steel and 4 cubic yards concrete

Attached driveway (for Dike plans, lower tunnel indicated here): 363 pounds steel and 14 cubic yards concrete

Construction details

Main slab dimensions: 46 1/2′ x 68′

Main slab area (actual outside on ground): 2,955 square feet

Weight reinforced (total) Concrete (4000 pounds per cubic yard) plus steel: 2,583 tons

Weight plain concrete (hoppers 4000 pounds per cubic yard): 6 tons

Weight hopper fill sand (3000 pounds per cubic yard): 25 tons

Weight of grain (60 pounds per bushel): 6,021 tons

Weight of structural steel and machinery: 5 tons

Gross weight loaded: 8,640 tons

Bearing pressure: 2.93 tons per square inch

Main slab thickness: 24″

Main slab steel (size and spacing): 1″ diameter,  5 1/2″ o. c.

Tank steel and bottom–round tanks (size and spacing): 5/8″ diameter, 9″ o. c.

Lineal feet of drawform walls: 400′ (no drive)

Height of drawform walls: 120′

Pit depth below main slab: None

Cupola dimensions (outside width x length x height): 13′ x 93′ x 8′

Pulley centers: None

Number of legs: None

Distributor Floor: None

Track sink: None

Full Basement: Yes

Electrical room: In elevator

Driveway width: None

Dump grate size: None

Columns under tanks: 4 columns 16″ square

Boot Leg and Head: None

Machinery details

Top conveyor: 30″ belt at 500 bushels per minute; 7,800 bushels per hour; 10 horsepower drive; Howell tripper.

Bottom Conveyor: 24″ belt at 600 bushels per minute; 5,800 bushels per hour; 7 1/2 horsepower drive

Remarks

Also built: Extended driveway on elevator

 

 

 

 

 

 

 

 

 

 

 

 

 

A photographic review of concrete elevator parts and components

Story and photos by Kristen Cart

Some time ago, one of our readers requested the picture of an elevator pit. It is one of the more unglamorous parts of a grain elevator, but as I was going through old photos, I found one. I also found many interior elevator pictures that have not made it to the blog because of their, well, unattractiveness. But a review of the parts and pieces, terms and descriptions, and interior appearance of an elevator is in order.

 The Pit

Pit access by ladder. The leg is visible.

Pit access by ladder. The leg is visible. Hanover, Kan.

DSC_0677(2)

Sloped bottom funnels grain to the base of the leg.

The Dump Grate

DSC_0674(2)

A smaller grate.

DSC_0292(1)

Center driveway truck grates.

The Driveway

DSC_0410

McCook, Neb.

DSC_0208(1)

St. Francis, Kan.

The Man Lift

DSC_0679(1)

The bottom of the lift showing the shaft.

DSC_0210(1)

Current safety regulations require a retrofitted cage.

Overhead bin spouts

Bins are numbered to correspond with the bin diagram

Bin Diagram

St. Francis, Kan.

St. Francis, Kan.

DSC_0295

This elevator holds beans in two overhead bins.

DSC_0670(1)

The bins hold milo, and “F” means the bin is full.

The Leg

DSC_0418

Cup dimensions and spacing are given in elevator specifications.

DSC_0673(1)

The leg conveys grain from the pit to the top of the bins.

Manhole Cover

Traer, Kan.

Traer, Kan.

 

Insights from a Ralston, Iowa, elevator maintenance worker

DSC_5966

At the far left edge of the photo, the annex can be seen behind the similarly sized elevator.

Story and photos by Kristen Cart

Each time we travel to Nebraska to see our family, I try to investigate elevators, and the kids groan and roll their eyes, pulling electronic entertainment out of their backpacks.

In March, our trip home warranted a stop at Ralston, Iowa, where we hoped to see an annex built by Tillotson Construction Company of Omaha as we trekked eastbound along U.S. Highway 30. Ralston is about midway across the state and lies south of the highway, and is the site of one of the projects documented in Tillotson company records.

The West Central Cooperative elevator complex, silent and lofty, rimmed the edge of town as we approached on a bright Sunday afternoon. Not a soul was in sight as we entered the parking lot near the cooperative headquarters. But a car in front of the office building was open with a shopvac beside it. Someone had to be around.

DSC_6016

A much larger group of elevators was behind me, away from the town, as I took the photo.

The elevator group in Ralston is dominated by a large squarish elevator, a multi-bin elevator, and a large, multi-bin, rectangular annex snugged in beside the latter. Between the first elevator and the second is an old wood elevator which immediately attracted my attention. It made a fine photographic subject. While shooting the scene, I looked for signs of a Tillotson project. Nowhere was there any manhole cover with the name of a builder. And no one was present who could give me a look inside.

The annex, slightly narrow than the elevator, is on the left

The annex, slightly narrower than the elevator, is on the left.

In fact, the deserted elevator group so dominated the town, along with its companion group of elevators a mile or so down the tracks, that it seemed intimidating to go near it. So I stood off and took photos from across the street.

DSC_6001Heavy rail traffic attended the tracks alongside the elevators in spite of the sleepy Sunday. I counted several trains, blaring their arrival as they passed through town.

At last, a fellow emerged from the cooperative building and commenced vacuuming the company car. I approached him to ask him about the elevators. Ron Hickey, of Farnhamville, Iowa, waved a friendly greeting. He said he was a bit of a newcomer to the Ralston site, but had worked at Boxholm, Iowa, the site of another Tillotson elevator, for two years before coming here. He said that Boxholm’s elevator had 96 florescent light bulbs, and until recently, he was responsible for cleaning every one of them.

Presently, he was cleaning one of several company vehicles parked in front of the nicely appointed offices. The place had every sign of prosperity. Ron said West Central was one of the largest cooperatives in Iowa, and was very successful.

Once we arrived home, I had to resort to the company records to positively identify Tillotson Construction’s contribution to the site. The specifications for Ralston fit the size of the annex I had seen–a massive structure about twice the size of the average elevator project. Since this structure was an annex, many items normally included in a complete elevator build were not required. The Tillotson construction details are reproduced below.

The Ralston storage was built in 1953 using the “Ralston Plan,” which had eight 28′ diameter, 115′ tall bins with a 2′ spread, flat bottoms, and a screw conveyor.

Capacity per plans: 537,000 bushels

Capacity per foot of height: 4,838 bushels

Reinforced concrete per plans (total): 2,779 cubic yards

Plain concrete (4″ hoppers and liner): 9 cubic yards

Reinforcing steel per plans (includes jack rods): 168.18 tons

Average steel per cubic yard of reinforced concrete: 121.00 lbs.

Steel and reinforced concrete itemized per plans

Below main slab: steel 3,128 lbs.; concrete 29 cubic yards

Main slab: steel 102,340 lbs.; concrete 606 cubic yards

Draw form walls: steel 203,034 lbs.; concrete 1,920 cubic yards

Driveway and work floor: not installed

Deep bin bottoms: not installed

Overhead bin bottoms: steel 4,666 lbs.; concrete 24 cubic yards

Bin roofs and extension roofs: steel 14,284 lbs.; concrete 112 cubic yards

Cupola walls: steel 8,907 lbs.; concrete 20 cubic yards

Distributor floor: concrete 2 cubic yards (steel included in above total)

Cupola roof: concrete 3 cubic yards (steel included in above total)

Miscellaneous (boot, leg, head, track sink, steps, etc.): not installed

Attached driveway (in this plan, a gallery, with cross tunnel not included): concrete 63 cubic yards (steel included in above total)

DSC_6010Construction details

Main slab dimensions: 66 2/3′ x 121 2/3′

Main slab area (actual outside on ground): 7,738 square feet

Weight reinforced concrete (4,000 lbs. per cubic yard plus steel): 5,726 tons

Weight plain concrete (4,000 lbs. per cubic yard): 18 tons

Weight hopper fill sand (3,000 lbs. per cubic yard): 154 tons

Weight of grain (60 lbs. per bushel): 16,125 tons

Weight structural steel and machinery: 20 tons

Gross weight loaded: 22,043 tons

Bearing pressure: 2.86 tons per square foot

Main slab thickness: 24 inches

Main slab steel (size and spacing): straight; 1 1/4 square inches and 8 inches o. c.

Tank steel and bottom (round tanks): 5/8 inch diameter and 6 inches

Lineal feet of draw form walls and extension: 717 feet 7 inches; 39 feet 6 inches

Height of draw form walls: 115 feet

Pit depth below main slab: 9 feet 6 inches

Cupola dimensions (outside width and length and height): 12′ x 14′ x 20′

Pulley centers: 137 1/2 feet

Number of legs: 1 main (see pulley center above) and 1 jack

Distributor flow: yes

Track sink: no

Full basement: no

Electrical room: no.

Driveway width-clear: not installed

Dump grate-size: not installed

Columns under tanks: not installed

Boot–leg and head: steel

Machinery details

Head pulley (main leg): 48″ x 16″ x 4 15/16″

Boot pulley: 48″ x 13″ x 2 3/16″

RPM head pulley: 48 rpm

Belt: 15″-6 ply calumet

Cups: 14″ x 7″ at 10″

Head drive: Howell 40 horsepower: 3

Theoretical leg capacity (cup manufacturer’s rating): 7,950 bushels per hour

Actual leg capacity (80% of theoretical): 6,350 bushels per hour

Horsepower required for leg (based on above actual capacity): 26.4 horsepower

Man lift: not installed

Load out scale: not installed

Load out spout: not installed

Truck lift: not installed

Dust collector system: fan into bin

Cupola spouting: not installed

Driveway doors: not installed

Conveyor: 24 inch screws

Also built

Track scale: 50 foot, 50 ton: concrete 35 cubic yards

 

 

 

 

The vanished Glidden elevator, a concrete giant, has gone the way of the wood

Story by Kristen Cart

It is tremendously disappointing when you realize an elevator should be there, and isn’t. I recently passed through the north-central Iowa town of Glidden, a small place mostly on the south side of Highway 30. I knew from Tillotson construction records that an elevator and an annex were built in Glidden back during the elevator boom. But though I leaned over to that side of the car to peer at the skyline, hoping to see the familiar white Tillotson elevator outline, all I saw were two hulking bins of another more modern sort.

You learn to expect old wooden elevators to disappear. But the 1940s and ’50s vintage concrete elevators usually are not so quick to go.

Glidden, IA 51443 - Google MapsThis situation would require some investigation, but not on a day when I had to get home, with another 400 miles or so to go. I had at least one more stop planned to see an elevator, at Ralston, a town just a few miles further east, and my three kids tolerated the stops, hanging in there at the frazzled edges of their patience.

When I got home, I resorted to the Internet. Satellite images have become so good that you can virtually identify a builder from above. But in the case of Glidden, there was no sign of an old elevator, only a bulldozed area where the forms for two circular bins had been laid out. Apparently I had not overlooked the desired elevator–it was gone.

NEW Cooperative Inc - Google MapsI didn’t count on being able to date the demolition, but the map’s “street view” came to the rescue. An uploaded photo, watermarked 2013, showed a view of the site from an intersection down the street. From that perspective, the old elevator stood as it always had, since it was built. So the old elevator was probably retired after the last of its grain was out, in time for new bins to be built for the next harvest, sometime in 2013 before winter set in.

I missed my grandfather’s (alleged) McAllaster, Kan., elevator by a couple of months when it was torn down over a year ago. But in the satellite image that was available at the time, you could see where the destruction had begun. Several round bins were newly absent, and holes appeared in the top of the headhouse.

I don’t imagine that satellite engineers envisioned this use for their images.

 

A tale from the Johnson Construction elevator at Galatia, Kansas

DSC_0582 copy Blencoe

Blencoe, Iowa

Story by Kristen Cart

Once again, one of our readers has supplied a fascinating glimpse into the construction of an elevator.

Emily Frank is the granddaughter of Darrell Greenlee, a foreman for Johnson and Johnson-Sampson. She related a story about the beginnings of the Galatia, Kan., grain elevator:

The Post Crescent 26 Mar 1959My grandfather built slipform concrete grain elevators while my mom was little. My grandparents moved around every three to six months from the time they were married until my mom (the third of six children) was in third grade. I find a lot of your stories remind me of the ones my mom told or my grandmother tells. You did one where a man fell to his death from an elevator during construction. Unfortunately that happened on a job where my grandfather was the foreman, as well…

My grandfather worked for Virgil Johnson. At the time the company was Johnson Elevator Company.

At a job in Galatia, Kan., in 1959, while Darrell was stabilizing the family trailer, it fell and he was hit across his back and shoulders. Rosina took him to the hospital. The hospital wasn’t going to see him until she could pay. She didn’t have insurance. She told them instead, “I’ve got enough money to buy this damn hospital.” When they left two days later, she paid cash.

Rosina called Virgil to tell him that Darrell had been hurt–not bad but he was pretty bruised up. Rosina wasn’t sure what they were going to do. She told Virgil she wanted to know what he was going to do because if Darrell didn’t work, he didn’t get paid. Virgil asked if his butt was bruised and then pointed to a chair and said “See that chair right there, he can park his ass right there and supervise from his chair.”

When the elevator was just about completed a man fell from the top of the elevator. Darrell was a witness to the fall. The guy opened the door at the top and the wind caught him and blew him over the side of the elevator. He fell 120 feet to his death. The man was Arthur Kronberg, 42, originally from Menasha, Wisconsin.

Rosina said when they called the man’s brother to tell him he could come pick up his belongings, he didn’t seem very interested, except he asked if there was anything of value. They had told him his brother had a truck. The man reluctantly agreed to get the truck.

Emily filled in some of the details of her grandfather’s career. The history of Johnson Elevator Company that she shared intrigued us, because the company took up where Mayer-Osborn Company left off and built strikingly similar elevators. The Galatia elevator is a close copy of the Mayer-Osborn elevators at McCook, Neb., and Blencoe, Iowa. Because of the similarities between them and a number of other Johnson elevators, we have speculated whether designer Gene Mayer continued his career with Virgil Johnson and brought his designs with him. Emily continued:

DSC_0574(1)

Page City, Kan.

The elevator at Galatia is on one of Johnson’s business cards.

Johnson used to work with some brothers with the last name Sampson. They were Virgil Johnson’s brothers-in-law. They worked together for a while, too, under the name Johnson-Sampson.

My grandfather worked constructing concrete elevators from 1947 to about 1963. He worked for several different people.

DSC_0526

Mitchellville, Iowa.

Johnson was the man he worked for most, on and off over the years. When Virgil and his brothers-in-law split, my grandfather went to work for Dewey Construction and then Young Love. Then Virgil found a partner, and my grandfather worked for Johnson & Bratcher. Then Virgil went off on his own as Johnson Elevator Company.

When Virgil went broke after a missile base job in the 1960s, my grandfather worked for a guy by the name of Guy James. He did two jobs for him until he finally settled in Rushville, Ill. He never built another elevator, but he had his own company and they did a lot of elevator repair work.

My own grandfather William Osborn’s experience followed a similar trajectory–after he was done with elevator construction, he went on to elevator repair and maintenance. We always attributed the cancer that took him at age 75 to the dust he breathed during those years, though some of the damage could have been from smoking, a habit he dropped ten years before he died.

The hazards of the business were sometimes obvious, but often stealthy and unexpected. From dust, to wind, to new boots, to heedless roofers, many things in elevator construction took lives–but the monuments built by these mortal men remain, withstanding tornadoes, floods, hail, and every natural disaster.