In the last post, we checked out two of Tillotson Construction Company’s earliest designs and their derivatives. In the 1940s, many elevator plans departed substantially from Tillotson’s first efforts, and they had plan names of their own. Some of those elevators were one-of-a-kind.

I will examine the orphan designs and a few that were used more than once, but failed to catch on, in the next two posts.

Orphan designs were unique storage plans, made to meet unusual customer needs. Non-standard-sized elevators were built to mimic Tillotson’s more basic offerings. Annexes were custom built. If an elevator and annex were built together, certain features were unique.

Here are the orphans of the 1940s.

Peterson Plan:

Peterson 01Peterson, Iowa (1944) was “storage, mainly,” with no driveway, a “x spout to leg,” and 12 1/2-foot-diameter tanks. It had a conveyor belt and a wooden, hand-operated man-lift. Its capacity was only 37,550 bushels. This was one of the smallest elevators Tillotson ever built, though a few were even smaller.

Farnsworth Plan:

Farnsworth, Tex. (1945) was the largest elevator Tillotson built to date, with a 350,000 bushel capacity. It had 19 bins with six 20-foot-diameter tanks, and a tunnel with a conveyor belt. A semi-truck driveway was built with a machine room directly overhead. Projects of this size were uncommon.

Peterson 02Farnsworth, Tex. will require a site visit, because we don’t know if a Tillotson elevator still stands. Three large elevators exist in Farnsworth, but none is typical of Tillotson’s style–two have hexagonal bins (the design made a big media splash in 1949), and the other could be a Tillotson, but looks more like a Chalmers and Borton elevator.

Dalhart Plan:

Dalhart, Tex. (1947) was a bit of an oddball, having an attached driveway rather than a center driveway. It had no basement and no distributor floor, but sported the “standard cupola.” It had four 20-foot-diameter tanks and could hold 150,000 bushels of grain. A 98,000-bushel annex was built alongside it at nearly the same time, which could explain the oddities: direct cross-spouts from the elevator provided gravity flow to the annex pit.

A second elevator was built in Dalhart, Tex., in 1949, which also gave is name to a plan: this “Dalhart Plan” described a large elevator with 310,000-bushel capacity.

Eva Plan:

Eva, Okla. (1947) was a very small elevator with only a 13,500 bushel capacity. The description says “cupola in D.F. [draw-form] wall.” The driveway was attached. It had two 14-foot bins, a “rope drive” and motor room.

Moscow Plan:

Moscow, Kan. (1948) is featured in an earlier post on this blog. It was a smallish elevator of 100,000 bushel capacity, four 14 feet-diameter tanks, and a 13 x 17 foot driveway with six bins directly overhead. It incorporated a dust bin.

DSC_0288

Minneapolis, Kan., mill building, elevator, and annex

Mill Building:

Minneapolis, Kan. (1948) is a site that fooled me on first examination. No manhole covers were evident on any structures except for the mill building. I didn’t expect an elevator with a rectilinear headhouse to be a Tillotson creation, so when we featured the mill building in our post (follow link), I added specifications which describe the elevator beside it! We will publish the mill building specifications in a later post.

Greenwood 01

Greenwood, Neb. ca. 1951 with attached Tillotson annex

Hordville Plan:

Hordville, Neb. (1949) was a 70,000 bushel capacity elevator with four twelve-foot-diameter tanks, a driveway, and eight bins directly above the driveway. Its rounded headhouse, by 1949, was already standard on Tillotson elevators.

Hordville’s outward appearance is a miniature version of Tillotson elevators of the same vintage–a style that continued into the early 1950s. Greenwood, Neb. (1951), which was built using the Churdan plan, circa 1949, is a larger-scaled example of the type.

Pierson Plan:

Pierson, Iowa (1949, storage) had a 80,200 bushel capacity, four 15 1/4 foot-diameter tanks, a dump pit, one way scale, a spout floor below the bin roof, and cross spouts. It was designated “storage,” a structure more like an annex than a self-contained elevator.

Clare Plan:

Clare, Iowa (1949) was built to hold 88,800 bushels of grain with four 15 1/4 foot-diameter tanks. It had a spout floor below the bin roof and an attached drive.

The artists of the Tillotson Construction Company–architects and engineers, those creative, ingenious men–were prolific producers during the 1940s when elevator technology bloomed. The flower of their achievements can be seen scattered across the prairies, either finding useful work, or passing into idleness, while curious onlookers snap their pictures and move on.

After the 1940s, almost all of the first Tillotson designs were dropped or modified as technology advanced. Only two designs (Churdan and Jackson) of the late 1940s carried into the 50s, and they were rapidly replaced after that, as will be seen in the next post.

2 comments on “Tillotson’s orphan designs of the 1940s gave way to popular elevator plans

  1. Linda Laird says:

    The first hexagonal grain elevator in the United States was built in 1946 by Chalmers & Borton in Enid OK for Union Equity Co-Operative Exchange as Elevator B (a common practice to label multiply built, same site elevators alphabetically). The hexagonal shaped elevator was built to maximize storage space by eliminating the curvilinear interstices of the tube elevator. The design was pioneered at the insistence of the elevator manager, E.N. Puckett who was inspired by a hotel bathroom tile design. Chalmers & Borton replicated the design infrequently in the 40s & 50s but hexagonal never really caught on. Good examples can be Googled at Hutchinson & Dodge City KS.

    The development of the new designs that Kristen is sharing with us shows the close cooperation between the builders & the managers which often led to diversity of design through accommodation to specific site needs. It also shows a willingness on the part of the builders, at this beginning of dynamic elevator growth, to be creatively responsive to clients. The flurry of experimentation eventually lead to more standardized plans of elevators with tweaking according to site & management needs. This period set the stage for the explosion of 1950s and 60s elevator building caused by the availability of federal loans to elevator owners and the federal policy to encourage storage of grain during the Cold War.

    • kocart says:

      Thank you Linda, for your interesting comment. I wonder if Tillotson ever built one of those hexagonal designs. I have not run into one, but wouldn’t it be interesting if they did? Chalmers and Borton was the eight-hundred pound gorilla for the smaller companies–the toughest competition they had. Chalmers and Borton got a lot of innovative work and large-scale projects, while Tillotson and Mayer-Osborn inhabited a mid-sized niche.

      In the 1950s Tillotson built more one-off designs, but these were special cases as more common designs proliferated. I will examine the 1950s as a follow-on to these posts.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s