The Tillotson elevator in Boxholm, Iowa, afforded unique photographic possibilities

DSC_0535Story and photos by Kristen Cart

The Boxholm elevator located in central Iowa was an intriguing destination, particularly since I had knowingly passed it by, missing it by a few miles on more than one trip. It became imperative to make the detour to see it. I was glad I did, since the elevator made beautiful pictures on that early summer day. I used a wide-angle lens that added pronounced distortion to the scene, causing the buildings on the edges to lean in dramatically. But the leaning lines pointed to the beautifully clouded sky.

You can use a wide-angle lens to include more of the scene from close quarters than would be possible with another lens, but you forfeit realism. This is not a problem for certain artistic photos, but it is not ideal for documentary shots. When photographing buildings where you want to preserve parallel lines, you must stand farther away and use a longer focal-length lens. At Boxholm, I did not have that option.

DSC_0547

Wide-angle lens distortion is maximized in this view.

At extremely close quarters, the wide-angle lens exaggerates height and adds drama. But the distortion becomes more pronounced.

The Tillotson Construction Company of Omaha, Neb., built the elevator in 1955. An annex stands beside it, and an old wooden feed mill is beside that. A much newer elevator with the West Central logo was built later, after it became customary to leave the concrete plain, without the white finish.

DSC_0563

A more conventional view of the elevator complex.

The specifications for the Boxholm elevator are among the Tillotson Company construction records. We learned some details about the elevator from a few stray sources before my visit; for instance, the elevator has exactly 96 light bulbs installed. Its construction followed the Drummond plan. Other projects using the same architectural plan were the elevators at Waverly, Neb., and Lahoma and Drummond, Okla.

Specifications

Capacity per plans (with Dock): 199,400 bushels

Capacity per foot of height: 2,002 bushels

Reinforced concrete per plans (total): 1,797 cubic yards

Plain concrete (3″ hoppers): 33 cubic yards

Reinforcing steel per plans (includes jack rods): 85.71 tons

Average steel per cubic yard reinforced concrete: 95.4 pounds

Steel and reinforced concrete itemized per plans:

Below main slab: 6,861 pounds steel, 59.2 cubic yards concrete

Main slab: 25,603 pounds steel, 202 cubic yards concrete

Drawform walls: 103,192 pounds steel, 1,295 cubic yards concrete

Driveway and Work floor : 3,820 pounds steel, 23.8 cubic yards concrete

Deep bin bottoms (including columns): 7,271 pounds steel, 39.3 cubic yards concrete

Overhead Bin bottoms: 6,040 pounds steel, 27.6 cubic yards concrete

Bin roof and Extension Roofs: 7,210 pounds steel, 41.7 cubic yards concrete

Scale floor (or garner complete): 160 pounds steel, 2.5 cubic yards concrete

Cupola walls (including leg & head): 7,257 pounds steel, 76 cubic yards concrete

Distributor floor: 1,560 pound steel, 9.4 cubic yards concrete

Cupola roof: 2,147 pounds steel, 15.6 cubic yards concrete

Misc. (track sink, steps, etc.): 173 pounds steel, 3.5 cubic yards concrete

Attached driveway: none

Bridge and/or Tunnel: none

Pit Liner–plain: 16 cubic yards concrete

Drier Bin Bottom: 134 pounds steel, 1.3 cubic yards concrete

Coffer Dam, Cleaner Floor: Wood

Remarks: 10 Bin Hot spot; 8 Bin Aeration tubes; Dryer bin

DSC_0541

The rounded headhouse is a reliable indicator of a Tillotson elevator

Construction details

Like Waverly: construction details were identical to Waverly and not listed separately in the records.

Main slab dimensions (drive length first dimension): 56 1/2′ x 70′

Main slab area (actual outside on ground): 3,850 square feet

Weight reinforced (total) concrete (4000 pounds per cubic yard plus steel): 3,747 tons

Weight plain concrete (hoppers; 4000 pounds per cubic yard): 98 tons

Weight hopper fill sand (3000 pounds per cubic yard): 732 tons

Weight of grain (at 60 pounds per bushel): 5,982 tons

Weight of structural steel and machinery: 20 tons

Gross weight loaded: 10,579 tons

Bearing pressure: 2.75 tons per square foot

Main slab thickness: 24″ with 3″ pile cap

Main slab steel: straight #9 at 7″ spacing

Tank steel and bottom (round tanks): #4 at 12″ spacing

Lineal feet of drawform walls & extension: 606′

Height of drawform walls: 120′

Pit depth below main slab: 15’3″

Cupola dimensions (outside width x length x height): 22 1/4′ x 48 1/2′ x 35′

Pulley centers: 160.75′

Number of legs: 1

Distributor floor: yes

Track sink: yes

Full basement: yes

Electrical room: yes

Driveway width clear: 13′

Dump grate size: 2 at 9′ x 5′ and 9′ x 15′

Column under tanks size: 16″ square

Boot legs and head: concrete

DSC_0531Machinery details

Boot pulley: 72″ x 14″ x 4 15/16″

Head pulley: 72″ x 14″ x 2 7/16″

R.P.M. Head pulley: 42

Belt: 335′, 14″ 6 ply Calumet

Cups: 12″ x 6″ at 8″ spacing

Head drive: Howell 40 horsepower [4 circled here]

Theoretical leg capacity (cup manufacturers rating): 8,440 bushels per hour

Actual leg capacity (80% of theoretical rating): 6,750 bushels per hour

Horsepower required for leg (based on actual capacity): 32 horsepower

Man lift: 1 1/2 horsepower Ehr.

Load out scale: 25 Bushel

Load out spout: 10″ diameter

Truck lift: 7 1/2 horsepower Ehr.

Dust collector system: Fan to bin

Cupola spouting: 10″ diameter

Driveway doors: 2 overhead rolling

Conveyor: provision

Remarks

see page 10 (above)

Night and day in 1950, Tillotson’s grain elevator rose in Alta, Iowa

scan0011

Commentary by Neil A. Lieb, photos from his archive

From a telephone interview on July 22, 2014:

It was commercial power for the lamps. The only thing that was noisy was the mixer and the hoist. Once you got about 40 feet off the ground, all that anybody heard was people talking to each other. That’s the top of the driveway (seen in the photo), about 16 feet, so they’re about 25 or 30 feet off the ground. On a construction site, there’s lumber all over everywhere. Today they keep track of it very carefully because people steal it. But when we were building these, nobody stole lumber. People in Iowa and the Midwest, they didn’t steal lumber from a construction site like they do out here (California.) See the scaffolding below the forms? A cement finisher finished the concrete as it came out of the forms. That’s all he did, all night long.

scan0012

Those cars…I didn’t have a car at Alta. Those shacks were probably, lower right, the office, and the other was where we kept the tools. We built a lot of those things and then we tore them down. Slip-form construction was a major engineering feat. They built concrete grain elevators before slip-forms. They had steel forms they’d fill with concrete.

 

 

 

The gun fired, and continuous action of many processes began in Alta, Iowa

scan0007

In this post, Charles J. Tillotson elaborates on Neil A. Lieb’s previous comments, describing the above photo from his archive. The jack rods referred to in the text are the tall, slender steel poles seen throughout the photo.  

They often say, a picture is worth a thousand words and this one fits the bill perfectly. The photo is truly an aid to describing the method of slipform construction that was used in grain elevator construction. Neil mentions the one-handed placement of the jack rod, so I’ll start with that.
 
Slipform construction is made up of many complex disciplines which have to all work together in order to provide the final poured-in-place concrete product.

As mentioned prior to this, the slipping of the formwork used in this type of construction was provided by a series of screw jacks placed apart by an engineered calculation sufficient to lift each jack’s portion of the formwork assembly.

Each screw jack was supported by a wooden, U-shaped yoke, the legs of which were attached to the vertical concrete formwork. Inserted in the top (or horizontal) portion of each yoke was a screw jack (similar to that used in jacking building foundations). A smooth one-inch jack rod was then inserted into the top head of the jack and threaded down through it until stopping at the foundation slab. 

The formwork is clearly seen at the Alta elevator rises. The catwalk around the bottom was for the concrete finisher, who smoothed and patched the freshly formed surface. Photo from the Neil A. Lieb Archive.

The wooden formwork is clearly seen at the Alta elevator rises. The scaffolding around the bottom was for the cement finishers, who smoothed and patched the freshly formed surface. Photo from the Neil A. Lieb Archive. 

A series of horizontal wooden rails at about waist height (looks like a railroad track) were then built directly above the open formwork, the “ties” of which were placed at prescribed intervals and used as a template spacer for inserting the actual vertical reinforcing steel. (See the small, half-inch rebar rods extending vertically out of the open bin forms at each cross tie). The vertical rebar was staggered slightly in an alternating fashion so as to allow the half-inch horizontal rebar to be threaded through the vertical rebar. On the vertical 2x4s that are attached to the exterior side of the formwork and rise above the entire deck assembly, so-called targets placed on their tops were used in leveling the deck in order to provide a final elevator that rose plumb and straight above the foundation.

As the screw jacks were turned (each jack was turned the same amount), the foreman on deck used a leveling instrument and sighted on each target to insure that the formwork was rising true plumb and level. If any of the targets did not align with true level, the portion of the deck out of plumb was corrected by extra turns of the screw jack or jacks as necessary to bring that portion of the deck up level with the rest of the formwork. 

Not shown in the photo is the horizontal rebar that was required to form a steel reinforced grid integrally cast in the concrete to form a reinforced concrete structure. Initially, the horizontal steel was wire-tied in place to the vertical rebar prior to one side of the forms being installed.  This placement occurred only to the height of the wood bin forms. Once the form-lifting began, the horizontal steel was placed by hand by pushing and threading the rebar horizontally through the vertical rebar. Because of the vertical movement of the formwork, close attention was required as to the spacing between horizontal rebar. 

Now, try to imagine: the start gun is fired and the continuous action of the many processes begins, never to stop until the wooden forms and finished structure reaches the prescribed vertical height (some 120 feet) eight days later. Manual labor is involved in each discipline. Personnel changes occur, but each position is filled by a replacement. The gun is fired, cement is mixed and lifted to the deck of the formwork via a Georgia buggy, and the content is dumped into the open form. The pouring of the cement into the formwork is continued in a circular fashion around the entire deck until it reaches a prescribed height in the form. 

The finished elevator. Photo from the Neil A. Lieb Archive.

The finished elevator. Photo from the Neil A. Lieb Archive.

Once the cement is allowed to solidify in the forms on the foundation slab, the jacking operation begins and the formwork starts its vertical lifting and slipping process. The jacks are turned, the cement is poured, the vertical rebar and jackrods are placed and spliced, and all the while the horizontal rebar is positioned at the proper height and spacing. Pour cement, turn jacks, place rebar, check deck level, and on and on through night and day until the construction reaches final height. The most problematic aspect of this system is the placing of the horizontal steel at the correct spacing, the placement of formed openings in the bins, keeping the hoist in operation, mixing the cement, and obtaining enough set time of the cement mixture so that as the finished concrete walls do not fall apart or slough off.     

Also, hanging beneath the formwork structure is the scaffolding for the cement finishers who dutifully serve to patch and smoothly finish the concrete surfaces appearing at the bottom of the vertically slipping formwork. 

 

 

Building a grain elevator required a whole boxcar of lumber

scan0009

Commentary by Neil A. Lieb, photos from his archive

From a telephone interview on July 22, 2014:

Decks for the formwork are stacked at upper-right corner of the foundation. Piles of sand and gravel are for concrete. It took one complete boxcar-load of lumber to build most elevators. Everything came by rail in those days.

One thing you did, you re-used all that lumber many, many times. The inside walls of forms were all taken down, taken apart, and the lumber was all reused. We always had a crew of two or three guys cleaning lumber, taking the nails out and cleaning the concrete off of it. Slip-form lumber was seldom reused. By the time you stripped the forms out at the top, that lumber fell 120 feet to a concrete slab and by the time it got there, it was moving. So when it hit, it pretty well disintegrated.

scan0010
This is probably the third or fourth day. They went about six inches an hour. The boxes were put in the forms to leave holes where they wanted a hole. On the inside, they’d want a hole to put a spout or something. They’re all pre-made and numbered. The shift foreman’s responsibility is to make sure they’re put in where they’re supposed to be. They have a given height and given location.

You always knew how high you were because in the elevator’s water shaft there was a continuous measuring stick so you knew exactly how high off the ground you were. It was important that these boxes be put in at a certain height.

You also had a continuous ladder. We used to race up and down.

You see the jacks are on the outside. The guys looking over the rails, this is the back side. Way on the other side is where the cement is coming up. You can’t see a hoist.

 

 

 

 

 

 

 

Stabbing jack rods one-handed and borrowing smokes in Alta, Iowa

scan0007Commentary by Neil A. Lieb, photo from his archive

In a telephone interview July 22, 2014, Neil describes this dramatic scene:

Everything is in place, I can tell you that. This is all ready to go. The big long ones are jack rods. if you follow them down you can see the jack. One-third into the picture from right, you can see the jack heads. You turn those a quarter turn at a time.

An interesting thing about jack rods, to impress the new hires, the old timers… They were eight-foot-long, one-inch cold-rolled steel weighing about 65 pounds. The trick was that you pick up the rod and put it in the jack with one hand. it was something you just did. Just to demonstrate ability, I guess. Everybody on the crew could stab a jack rod one-handed.

Around the outside wall, the thin rods are vertical rebar. If you look in the middle, you can see the hold that the concrete goes in.

Bracing for the hoist is what cuts across the roofline of the house.

Wayne Baker, foreman, is probably the one striding through the middle. Baker never bought cigarettes. When I worked in construction, everybody smoked. I don’t ever remember seeing him pull out a pack of cigarettes.

A Tillotson skyscraper dominates corn country in Randall, Iowa

DSC_0638

Story and photos by Kristen Cart

During every elevator scouting trip, there comes a fork in the road where we choose which elevator to see, and which to save for another time. On the way home from Nebraska this summer we came to such a place at the junction of Iowa Route 175 and US 69 in central Iowa. To the north I could see the silhouette of an elevator at Jewell, and just east from Jewell, across the South Skunk River, the town of Ellsworth beckoned. But as I checked my map, to the south I saw Randall, which was a familiar name. I elected to turn south onto US 69.

The name should have been familiar, because it is found in several places in the Tillotson Construction Company records. The elevator in the central Iowa town of Randall was built in 1949 using the “Dike Plan.”

DSC_0662

The elevator commands the Randall skyline

In the company records for subsequent projects at West Bend and Pocahontas, Iowa, both built using the Dike plan, the quantities of concrete and steel and the machinery details were summarized with the shorthand, “Like Randall,” for each project. The Dike plan was widely used for Tillotson’s quarter-million-bushel elevators.

The Randall elevator and its annexes overlooked a silent street of empty storefronts on that quiet Sunday. The co-op office looked new and efficient. The town was a perfect snapshot of the principle of economy-of-scale: the small business, like the small farm operation, must grow, combine forces, or die.

We have the construction records for Randall’s elevator and its siblings in West Bend and Pocahontas, which vary in minor details. Randall’s specifications follow.

DSC_0644

The Randall Lumber Co. appears to be a survivor of the economic slump.

 

Specifications

Capacity per plans (with Dock): 252,000 bushels

Capacity per foot of height: 2,520 bushels

Reinforced concrete per plans (total): 2,066 cubic yards

Plain concrete (hoppers): 40 cubic yards

Reinforcing steel per plans (including jack rods): 109.37 tons

Average steel per cubic yard reinforced concrete: 106 pounds

Steel and reinforced concrete itemized per plans:

Below main slab: 4,637 pounds steel, 40 cubic yards concrete

Main slab: 39,291 pounds steel, 266 cubic yards concrete

Drawform walls: 129,000 pounds steel, 1,430 cubic yards concrete

Work and Driveway floor (including columns): 3,700 pounds steel, 24 cubic yards concrete

Deep bin bottoms: 11,832 pounds steel, 58 cubic yards concrete

Overhead Bin bottoms: 4,876 pounds concrete, 30 cubic yards concrete

Bin roof (or garner): 8,791 pounds steel, 56 cubic yards concrete

Scale floor (complete): none

Cupola walls: 8,404 pounds steel, 92 cubic yards concrete

Distributor floor: 1,848 pound steel, 11 cubic yards concrete

Cupola roof: 2,360 pounds steel, 18 cubic yards concrete

Misc. (boot, leg, head, track sink, steps, etc.): 3,000 pounds steel, 30 cubic yards concrete

Attached driveway: 1000 pounds steel, 11 cubic yards concrete (driveway extension, walls and roof)

DSC_0664Construction details

Main slab dimensions (drive length first dimension): 60′ x 72 1/2′

Main slab area (actual outside on ground): 4,200 square feet

Weight reinforced (total) concrete (4000 pounds per cubic yard plus steel): 4,241 tons

Weight plain concrete (hoppers 4000 pounds per cubic yard): 74 tons

Weight hopper fill sand (3000 pounds per cubic yard): 985 tons

Weight of grain (at 60 pounds per bushel): 7,560 tons

Weight of structural steel and machinery: 20 tons

Gross weight loaded: 12,880 tons

Bearing pressure: 3.06 tons per square foot

Main slab thickness: 21″

Main slab steel: bent 1″ square at 7″ o. c. spacing

Tank steel and bottom (round tanks): 1/2″ diameter at 9″ o. c. spacing

Lineal feet of drawform walls: 655 excluding extension

Height of drawform walls: 120′

Pit depth below main slab: 14’9″

Cupola dimensions (outside width x length x height): 24 1/2′ x 50 1/4′ x 40′

Pulley centers: 165.25′

Number of legs: 1

Distributor floor: yes

Track sink: yes

Full basement: yes

Electrical room: yes

Driveway width clear: 12′

Dump grate size: 2 at 9′ x 6′ and 9′ x 14′

Column under tanks size: 20″ square

Boot legs and head: concrete

DSC_0635Machinery details

Boot pulley: 72″ x 14″ x 2 3/16″

Head pulley: 72″ x 14″ x 3 15/16″

R.P.M. Head pulley: 42

Belt: 355′, 14″ 6 ply Calumet

Cups: 12″ x 6″ at 8 1/2″ o. c. spacing

Head drive: Howell 40 horsepower [3 circled here]

Theoretical leg capacity (cup manufacturers rating): 7,920 bushels per hour

Actual leg capacity (80% of theoretical rating): 6,340 bushels per hour

Horsepower required for leg (based on above actual capacity plus 15% for motor): 32 horsepower

Man lift: 2 horsepower Ehr.

Load out scale: 10 Bu. Rich.

Load out spout: 10″ w.c.

Cupola spouting: 10″ diameter 14 gauge

Truck lift: 7 1/2 horsepower Ehr.

Dust collector system: Fan to bin

Driveway doors: 2 overhead rolling

Conveyor: provision

Remarks

3 bin distributor under scale

Provision for hopper scale

 

 

 

 

The Alta, Iowa, grain elevator’s unique layout was ‘a different kind of job’

scan0009

Commentary by Neil A. Lieb and photos from the Neil A. Lieb Archive

This post’s two photos show early stages of work on Tillotson Construction Company’s grain elevator at Alta, Iowa, in the spring of 1950. In a July 22 phone conversation, Neil Lieb, who worked on this elevator as a Tillotson employee (1949 to 1951) described details:

Three tanks on right, two on left, a square tank on left … The little tanks were a lot more trouble to make. Alta was not designed by Tillotson. It was designed by some outfit out of Kansas City. So it was a different kind of a job, and it was specifically designed—they had some kind of a grain-drying system that was relatively new. When these [elevators] were built, they didn’t dry the grain. It had to be dry before you put it in. Alta had some kind of a drying system. These bins were all designed—the whole idea was you could have smaller quantities of grain stored that was wet, and you’d run it out of these bins and through the dryer into the bins below. Half full of wet grain, the other half full of dry. The dry was taken back and dumped in the major silos.

scan0008

 

The co-ops in Iowa were very large in those days, with hundreds of members signed up. They would take a sample out of the load and do a moisture content test. So they would test each load and put it in one of these tanks based on how much moisture it had. When they went to dry it, it would take out the required amount of moisture. I know we had a lot of extra electrical work.

The plans for the elevator are inscribed on the elevator [slab], so you could set the forms where they belonged. The scribing was done a couple of days after the slab was poured. So when you build forms and moved them in, you knew exactly where to put them. It looked like it was all hit and miss, but it wasn’t.

Sixteenpenny nails were used in nailing together the forms. When you’re doing this, the foreman will count heads. You make all these interior pieces before you do anything else. When you make these, the foreman counts out heads, and he opens that many kegs of sixteenpenny nails, and they’re all supposed to be empty when you go home at night. Fifty-pound kegs and twenty-ounce hammer, and you start the nail and drive it with three strokes. The nail is a little over seven inches long. When you do that all day long for several days, you develop a real good right arm.