Comparing Mayer-Osborn elevators in Byers, Colorado, and McAllaster, Kansas

By Gary Rich

It is somewhat strange that you can have a company build an elevator, but there can be differences between two separate models. The Byers, Colorado, elevator was built by Mayer-Osborn. This model has the manhole covers on the outside of the bins, whereas the McAllaster, Kansas, elevator has the manhole covers on the inside. You will notice the manhole covers on the outside of the bins in the Byers view. Plus, there is a walkway door about halfway between the bins. The window arrangements are slightly different between these two elevators. Basically the driveway is the same on the two models.

One thing stands out like a sore thumb: whoever painted the Byers elevator painted the manhole covers. This is the only elevator where I have seen this done. Generally the manhole covers are not painted.

It would be the option of the Co-op what was wanted in the elevator. If the owners chose more options, of course the price of the elevator would increase, too.

There are two sides of an elevator. One is the track side, where the railroad tracks are located. The other side is known as the drive way, where the trucks will dump their loads.

I do not believe that the McAllaster, Kansas, elevator has been used for some years. The steel bins were empty, when I photographed here on November 14, 2011. The weeds were fairly high, and the rail spur has been removed. 

Mayer-Osborn Construction completes 450,000-bushel elevator in Burley, Idaho

Burley, July 22–Charles Barnes, manager of Union Seed company here, announced Friday that work is nearly completed on the new grain elevators and storage tanks west of town. He said the tanks, built to store all types of grain, have a capacity of about 450,000 bushels,

Eash of the 23 tanks is 135 feet tall and is made from six inches of reinforced concrete. The head house is 165 feet high, equivalent to a 16-story building. The tanks will be used to handle individual and Union Seed storage needs.

Barnes said that about 20,000 sacks of cement had been used in the construction under contract by Mayer-Osborn Construction company, Denver. He said the latest grain cleaning machinery has been installed, along with scales large enough to weigh the largest trucks, and that there are conveyer belts in both the head gallery and the basement tunnel.

Times-News, Twin Falls, Idaho, July 22, 1955

 

Tillotson Construction’s elevator at Dalton, Nebraska, shows unique features

Gary Rich contributed these photos from Dalton, Nebraska, along with the following analysis:

Tillotson Construction’s elevators were unique, with some features that I have not seen from other elevator builders. One major feature was the curved head house. I have only seen one other company that produced an elevator with the curved headhouse. Another feature was that Tillotson put windows for light into the basement. Of course they had electric lights in the basement. I have not seen another builder put windows in the bottom part of the elevator. This must be a Tillotson trademark. This elevator has the year of construction added to the manhole covers. It shows 1958. Tillotson did a great thing by adding this. All the elevators that I have been inside, I have not seen another company put the year on the manhole covers. The date was on each manhole cover inside the elevator.

Thompson, Iowa, elevator completed in 1950, torn down in early 1980s

Work Underway on Storage Elevator

Thompson – Work has been started on a 125,000 bushel storage elevator for the local co-operative elevator company by the Tillotson Construction company of Omaha, Nebr.

Mason City (Iowa) Globe-Gazette, June 20, 1950

Mason City Globe-Gazette, September 2, 1950

♦ ♦ ♦

Our call to the Farmers Cooperative elevator in Thompson, Iowa, while preparing this post resulted in a conversation with location manager Lyle Wirtjes, who said he started working at the elevator in 1969. By then, Mr. Wirtjes said, one silo had already “busted out.” After another such incident, a new elevator was constructed across the road and the Tillotson elevator was torn down sometime in the early 1980s.

♦ ♦ ♦

Kristen’s analysis:

This Thompson elevator should not have failed—look at Greenwood, still here after all these years. I would guess there were some corrupt people in the building trades pulling off a scam, and since so many projects were going at once, a few poorly done elevators slipped through. They all looked like carbon copies of one another, so unless soil, water table problems, or fire caused the break, crooked subcontractors could have caused it. Not an uncommon problem when the federal cash spigot is turned on full blast—everyone shows up to the party, whether good or not.  My speculation here.  Nineteen years is not much of a lifetime for an elevator, barring a fire.


Painting a concrete grain elevator in Lincoln, Nebraska

Merle Ahrens, uncle of Ronald Ahrens, has written an account of his summer of 1955, which was spent on a scaffold with another of Ronald’s uncles, Michael Tillotson, youngest son of Reginald and Margaret Tillotson:

After graduating from Omaha North High School in 1955, I went to work for Tillitoson Construction on a grain elevator in Lincoln, Nebraska, with Michael Tillotson. I was paid $1.25 an hour.

Merle at home

Merle Ahrens in 2011, at home in Titusville, Fla.

I remember the first day on the job we had to go to the top of the grain storage tank—at least 100 feet—on a bucket that was used to haul up concrete. The bucket was connected to the swinging boom at the top by a wire cable. The cable went to a stationary, manually operated, rotating spool, which wound up the cable to lift the bucket. The operator let it free-fall down, seeing how close to the ground the bucket and riders could get before hitting the brake. It was a scary ride with four or five other workers standing on the rim of the bucket, especially the free fall down. Thankfully, it didn’t take long to get used to.

At the top, there were no rails around the edges nor any safety provisions like you see today, just one jack rod sticking out of the surface to hold on to as you got on and off of the bucket. The first day, I spent a lot of time holding onto that rod looking over the side.

When Michael and I started work, all the concrete pouring was complete and we were given the task of painting the outside of the whole elevator. We painted it using a lime-base whitewash. We had to crawl over the edge of the top of the tank onto a flying scaffold. The scaffold was held up by a pair of rope block-and-tackles connected to a pair of wood beams that were extended about two feet over the edge of the tank. The wood beams extended about ten feet inboard and were weighed down with sandbags to keep the scaffold from falling. The scaffold was made up of a pair of two-by-twelve boards with a metal frame at each end and two-by-four railings around it. The rope block and tackles were attached to the scaffold on the ground. We had to pull the scaffold up to the top every time for each ten-foot width we painted. There was an old man on the ground who mixed the paint and pulled it up to us in a five gallon bucket. He had a harder job than we had. All we had to do was brush on the paint and pull the rope to release the half hitch that held up the scaffold and let gravity work to lower it. The “flying” part of flying scaffold was when the wind was blowing. You would fly halfway around the tank.

Every night we would take off our Levi’s and stand them in a corner. There was so much paint on them! Yet one pair lasted all summer.

After a couple of months we finished painting the elevator in Lincoln and went to David City to paint another grain elevator. This time we used a new latex paint. It was very slow-drying and the wind kicked up a lot of dust. The elevator ended up white with grey stripes.

We kept hearing of accidents at other sites. One man was said to have fallen from a plank used to walk between the top of two tanks. He was wearing new boots and slipped. Another was killed when roofers removed the sandbags holding the beam for the flying scaffold so they could hot-tar the roof. A couple more were hurt while riding on a bucket and the clamps holding the cable slipped. The clamps were installed wrong. I do know for a fact that one worker at Lincoln was hit in the face when a five-gallon bucket with concrete in it fell while he was using a rope and pulley to lift it overhead.

At the end of the summer, Michael went back to North High, and I went to work for the Union Pacific Railroad.

Merle Ahrens

January 9, 2012

December 1950: Tillotson Construction’s Jess Weiser weds Lavonne Wiemers in Palmer, Iowa

Miss Lavonne Wiemers, daughter of the late Mr. and Mrs. B.R. Wiemers, and Jess Weiser, son of O.S. Weiser of El Reno, Oklahoma, were married Friday evening, Dec. 22, in St. Paul’s Lutheran church in Palmer, the Rev. R. Wagner performing the ceremony.

Miss Darlene Wiemers was maid of honor, and bridesmaids were Mrs. Kendall Peterson of Fonda and Mrs. George Mart of Estherville, all sisters of the bride, and Miss Norma Schoon of Palmer, friend of the bride.

Flower girl was Janet Peterson, and ring bearer was Tommy Mart, nephew of the bride.

Roger Osborne and George Christian served as attendants to the bridegroom. Ushers were Paul Wiemers and Kendall Peterson.

Following the ceremony a reception was held at the Palmer Legion hall for 75 guests.

Mrs. Weiser, a graduate of Palmer high school, has been employed in Palmer. The bridegroom graduated from Yukon, Okla., high school and served in the Air Transport Command for three years. He is employed by the Tillotson Construction Co. Mr. and Mrs. Weiser will make their home in Storm Lake.

Pomeroy (Iowa) Herald, January 11, 1951

Maxine Carter leaves Tillotson Construction to wed

Miss Maxine Carter, daughter of Mr. and Mrs. Leland Carter of Corning, Iowa, and Russell L. Bentley, so of Mr. and Mrs. Edgar Bentley of Marathon, Iowa, were united in marriage Saturday morning, October 8, by Rev. C.D. Reed, in the First Methodist church in Council Bluffs, Iowa.

Miss Catherine Dakir of Omaha, Nebraska, was bridesmaid, and William LePine, also of Omaha, Nebr., was best man.

The bride wore a toast color suit with green accessories. Her corsage was light pink roses tinted with brown. The groom wore a dark blue suit.

The bride was a graduate of Corning high school in 1948, then attended Commercial Extension Business College in Omaha, Nebr., graduating in April, 1949. She was then employed as secretary to the Tillotson Construction Company of Omaha until the 7th of October.

The groom graduated from Marathon high school in 1947, then attended National Railroad School in Omaha, graduating in July, 1949. He is now with the Chicago, Milwaukee, St. Paul and Pacific railroad.

The couple are waiting until the groom gets his first vacation for their honeymoon.

We extend our sincere congratulations to the newly weds.

Adams County (Iowa) Free Press, Oct. 13, 1949